← 2026-03-08

Monday, March 9, 2026

2026-03-10 →
3,004MWh Curtailed
3,279MWh Ramped Up
€0.97MEst. Cost
272 MWPeak Positive

Day-Ahead Spot: 20-279 €/MWh (avg 127)

TSO Breakdown

TSODirectionMeasuresTotal MWh
Amprion positive 14 15,723
50Hertz negative 37 13,763
TransnetBW negative 3 8,732
TenneT DE positive 12 6,842
TransnetBW positive 11 4,142
TenneT DE negative 9 3,568
Amprion negative 9 3,147
50Hertz positive 1 405

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 TransnetBW Konventionell negative 737 7,926 12:March-23:March
Emsland Block D Amprion Konventionell positive 413 4,444 05:March-15:March
Netzreservekraftwerk Bexbach A Amprion Konventionell positive 388 3,205 13:March-21:March
illwerke vkw AG TransnetBW Sonstiges positive 288 2,302 12:March-23:March
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 375 2,251 08:March-14:March
HAMMUENTROP_10 Amprion Konventionell positive 254 2,220 06:March-15:March
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 203 1,825 07:March-16:March
Jänschwalde (Standort) 50Hertz Konventionell negative 299 1,792 07:March-15:March
ReserveKW Staudinger 5 TenneT DE Konventionell positive 228 1,656 06:March-13:March
ReserveKW Staudinger 5 TenneT DE Konventionell positive 216 1,562 14:March-21:March
Netzreservekraftwerk Bexbach A Amprion Konventionell positive 228 1,538 16:March-23:March
Boxberg (Standort) 50Hertz Konventionell negative 228 1,141 07:March-12:March
Lippendorf 50Hertz Konventionell negative 309 926 06:March-09:March
Schkopau 50Hertz Konventionell negative 307 921 07:March-10:March
Wilhelmshaven (ENGIE) TenneT DE Konventionell positive 183 915 09:March-14:March
50H PV Witznitz 50Hertz Erneuerbar negative 181 905 09:March-14:March
BAG NWAK-Cluster 14 Schwandorf TenneT DE Erneuerbar negative 240 900 09:March-13:March
NIEDERAUSSEM_K Amprion Konventionell negative 256 896 09:March-13:March
Emsland Block D Amprion Konventionell positive 296 889 10:March-14:March
Emsland Block D Amprion Konventionell positive 485 849 14:March-16:March
Wilhelmshaven (ENGIE) TenneT DE Konventionell positive 192 816 09:March-14:March
LAUSWARD_GUDF Amprion Konventionell positive 317 792 08:March-10:March
STUMMHAFEN_10 Amprion Konventionell positive 308 771 09:March-11:March
BAG NWAK-Cluster 15 Pleinting TenneT DE Erneuerbar negative 203 762 09:March-13:March
ReserveKW Staudinger 5 TenneT DE Konventionell positive 199 748 11:March-14:March
NIEDERAUSSEM_K Amprion Konventionell negative 148 739 09:March-14:March
Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 TransnetBW Konventionell negative 326 571 23:March-00:March
50H Berlin Mitte 50Hertz Konventionell negative 114 569 06:March-11:March
BAG NWAK-Cluster 17 Altheim TenneT DE Erneuerbar negative 150 562 09:March-13:March
illwerke vkw AG TransnetBW Sonstiges positive 255 446 23:March-00:March
Wilhelmshaven (ENGIE) TenneT DE Konventionell negative 30 442 00:March-23:March
WEISWEILER_G Amprion Konventionell negative 205 410 12:March-14:March
50H Hamburg Tiefstack 2 HKW SK 50Hertz Konventionell positive 70 405 08:March-14:March
50H Berlin Marzahn 50Hertz Konventionell negative 98 392 05:March-09:March
WALSUM_10 Amprion Konventionell negative 153 382 13:March-16:March
BAG NWAK-Cluster 12 Pirach-Simbach TenneT DE Erneuerbar negative 100 375 09:March-13:March
Linden GKL GT 1 TenneT DE Konventionell positive 65 371 06:March-12:March
NIEHL-II Amprion Konventionell positive 170 340 09:March-11:March
Börse TransnetBW Sonstiges positive 60 316 06:March-20:March
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 125 314 06:March-09:March
Heizkraftwerk Altbach/Deizisau Block 2 TransnetBW Konventionell positive 114 312 12:March-15:March
50H OWP Baltic Eagle 50Hertz Erneuerbar negative 74 295 09:March-13:March
BAG NWAK-Cluster 03 Bergrheinfeld-Schweinfurt TenneT DE Erneuerbar negative 100 275 10:March-13:March
Heizkraftwerk Altbach/Deizisau GT C TransnetBW Konventionell positive 80 260 15:March-19:March
Börse TransnetBW Sonstiges negative 118 235 05:March-15:March
Linden GKL GT 3 TenneT DE Konventionell positive 40 223 08:March-13:March
Boxberg (Standort) 50Hertz Konventionell negative 73 218 09:March-12:March
Emsland Block D Amprion Konventionell negative 273 205 21:March-21:March
50H OWP Arkona 50Hertz Erneuerbar negative 68 203 10:March-13:March
HAMMUENTROP_10 Amprion Konventionell positive 88 198 09:March-11:March

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.29M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-03-09?

On 2026-03-09, estimated redispatch costs were approximately €0.97 million. This includes €0.3M for renewable curtailment compensation and €0.51M for conventional ramp-up costs.

Which power plants were most affected on 2026-03-09?

The most affected plant was Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 (TransnetBW) with 7,926 MWh of negative redispatch.

What was the electricity spot price on 2026-03-09?

The EPEX Day-Ahead spot price for DE_LU ranged from 20 to 279 €/MWh with an average of 127 €/MWh.