4,389MWh Curtailed
7,117MWh Ramped Up
€3MEst. Cost
472 MWPeak Positive
Day-Ahead Spot: 230-574 €/MWh (avg 315)
TSO Breakdown
| TSO | Direction | Measures | Total MWh |
|---|---|---|---|
| Amprion | negative | 7 | 4,046 |
| TenneT DE | positive | 6 | 1,396 |
| 50Hertz | negative | 2 | 279 |
| TenneT DE | negative | 3 | 264 |
| TransnetBW | positive | 1 | 86 |
| 50Hertz | positive | 1 | 29 |
| TransnetBW | negative | 1 | 25 |
Plant-Level Redispatch Measures
| Plant | TSO | Fuel | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|---|
| WEISWEILER_G | Amprion | Konventionell | negative | 151 | 1,207 | 07:October-15:October |
| WEISWEILER_G | Amprion | Konventionell | negative | 203 | 1,065 | 01:October-06:October |
| WEISWEILER_H | Amprion | Konventionell | negative | 200 | 750 | 00:October-04:October |
| Gebersdorf 1 | TenneT DE | Konventionell | positive | 90 | 718 | 23:October-07:October |
| WEISWEILER_G | Amprion | Konventionell | negative | 89 | 715 | 23:October-07:October |
| 50H_TEN_CR_M2_VIB | 50Hertz | negative | 125 | 250 | 09:October-11:October | |
| Irsching 4 | TenneT DE | Konventionell | negative | 40 | 237 | 07:October-13:October |
| ReserveKW Plattling | TenneT DE | Konventionell | positive | 29 | 221 | 01:October-09:October |
| Gebersdorf 1 | TenneT DE | Konventionell | positive | 80 | 220 | 20:October-23:October |
| WEISWEILER_G | Amprion | Konventionell | negative | 80 | 220 | 20:October-23:October |
| Frankfurt West 4 | TenneT DE | Konventionell | positive | 60 | 180 | 10:October-13:October |
| Börse | TransnetBW | Sonstiges | positive | 69 | 86 | 01:October-15:October |
| Knapsack 1 | Amprion | Konventionell | negative | 66 | 50 | 05:October-06:October |
| Frankfurt West 5 | TenneT DE | Konventionell | positive | 15 | 45 | 07:October-10:October |
| CHEMIEPARK_MARL_KRAFTWERKE | Amprion | Konventionell | negative | 26 | 39 | 04:October-06:October |
| Boxberg (Standort) | 50Hertz | Konventionell | negative | 14 | 29 | 06:October-08:October |
| Thyrow A (SysRel) | 50Hertz | Konventionell | positive | 14 | 29 | 06:October-08:October |
| Börse | TransnetBW | Sonstiges | negative | 33 | 25 | 01:October-15:October |
| Irsching 5 | TenneT DE | Konventionell | negative | 25 | 25 | 08:October-09:October |
| Frankfurt West 3 | TenneT DE | Konventionell | positive | 6 | 12 | 08:October-10:October |
| Börse | TenneT DE | Sonstiges | negative | 10 | 2 | 23:October-23:October |
How BESS Can Reduce These Costs
Battery Energy Storage Systems at congestion points could have avoided an estimated €0.9M of today's redispatch costs by absorbing excess wind energy locally.
Learn BESS Arbitrage (Free) Stromfee AI PlatformFrequently Asked Questions
How much did redispatch cost on 2026-10-29?
On 2026-10-29, estimated redispatch costs were approximately €3 million. This includes €0.44M for renewable curtailment compensation and €2.46M for conventional ramp-up costs.
Which power plants were most affected on 2026-10-29?
The most affected plant was WEISWEILER_G (Amprion) with 1,207 MWh of negative redispatch.
What was the electricity spot price on 2026-10-29?
The EPEX Day-Ahead spot price for DE_LU ranged from 230 to 574 €/MWh with an average of 315 €/MWh.