4,488MWh Curtailed
6,302MWh Ramped Up
€2.45MEst. Cost
329 MWPeak Positive
Day-Ahead Spot: 211-350 €/MWh (avg 269)
TSO Breakdown
| TSO | Direction | Measures | Total MWh |
|---|---|---|---|
| TenneT DE | negative | 4 | 1,005 |
| TransnetBW | positive | 1 | 15 |
| TransnetBW | negative | 1 | 10 |
Plant-Level Redispatch Measures
| Plant | TSO | Fuel | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|---|
| Irsching 5 | TenneT DE | Konventionell | negative | 95 | 615 | 08:October-15:October |
| Irsching 4 | TenneT DE | Konventionell | negative | 92 | 185 | 11:October-13:October |
| Irsching 5 | TenneT DE | Konventionell | negative | 88 | 175 | 11:October-13:October |
| Wilhelmshaven | TenneT DE | Konventionell | negative | 60 | 30 | 11:October-13:October |
| Börse | TransnetBW | Sonstiges | positive | 30 | 15 | 08:October-15:October |
| Börse | TransnetBW | Sonstiges | negative | 40 | 10 | 12:October-13:October |
How BESS Can Reduce These Costs
Battery Energy Storage Systems at congestion points could have avoided an estimated €0.74M of today's redispatch costs by absorbing excess wind energy locally.
Learn BESS Arbitrage (Free) Stromfee AI PlatformFrequently Asked Questions
How much did redispatch cost on 2026-10-30?
On 2026-10-30, estimated redispatch costs were approximately €2.45 million. This includes €0.45M for renewable curtailment compensation and €1.88M for conventional ramp-up costs.
Which power plants were most affected on 2026-10-30?
The most affected plant was Irsching 5 (TenneT DE) with 615 MWh of negative redispatch.
What was the electricity spot price on 2026-10-30?
The EPEX Day-Ahead spot price for DE_LU ranged from 211 to 350 €/MWh with an average of 269 €/MWh.