2,485MWh Curtailed
2,367MWh Ramped Up
€0.7MEst. Cost
130 MWPeak Positive
Day-Ahead Spot: 76-133 €/MWh (avg 99)
TSO Breakdown
| TSO | Direction | Measures | Total MWh |
|---|---|---|---|
| TenneT DE | negative | 31 | 72,809 |
| TenneT DE | positive | 11 | 37,430 |
| TransnetBW | positive | 13 | 31,373 |
| Amprion | positive | 17 | 29,611 |
| 50Hertz | negative | 19 | 10,524 |
| Amprion | negative | 8 | 4,562 |
| TransnetBW | negative | 3 | 1,768 |
| 50Hertz | positive | 6 | 860 |
Plant-Level Redispatch Measures
| Plant | TSO | Fuel | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|---|
| Börse | TenneT DE | Sonstiges | positive | 1063 | 23,389 | 23:February-23:February |
| Wilhelmshaven (ENGIE) | TenneT DE | Konventionell | negative | 578 | 13,874 | 23:February-23:February |
| Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 | TransnetBW | Konventionell | positive | 507 | 11,656 | 00:February-23:February |
| UW Büttel | TenneT DE | negative | 643 | 11,572 | 05:February-23:February | |
| AVA Cluster Voslapp | TenneT DE | negative | 494 | 11,125 | 00:February-23:February | |
| Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 | TransnetBW | Konventionell | positive | 310 | 7,447 | 23:February-23:February |
| Knapsack 1 | Amprion | Konventionell | positive | 471 | 7,306 | 04:February-19:February |
| WALSUM_10 | Amprion | Konventionell | positive | 532 | 7,180 | 05:February-19:February |
| UW Büttel | TenneT DE | negative | 880 | 5,281 | 23:February-05:February | |
| ReserveKW Staudinger 5 | TenneT DE | Konventionell | positive | 389 | 4,765 | 23:February-23:February |
| Emsland Block D | Amprion | Konventionell | positive | 311 | 4,663 | 08:February-23:February |
| ReserveKW Zolling 5 | TenneT DE | Konventionell | positive | 228 | 4,105 | 23:February-17:February |
| Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 | TransnetBW | Konventionell | positive | 535 | 3,742 | 23:February-06:February |
| ReserveKW Staudinger 5 | TenneT DE | Konventionell | positive | 318 | 3,182 | 13:February-23:February |
| Reservekraftwerk Altbach/Deizisau Block 1 | TransnetBW | Konventionell | positive | 233 | 3,150 | 23:February-12:February |
| UW Dörpen-West | TenneT DE | negative | 200 | 3,000 | 06:February-23:February | |
| SHN Cluster Klixbüll | TenneT DE | negative | 193 | 2,650 | 09:February-23:February | |
| SHN Cluster Süderdonn T411 | TenneT DE | negative | 185 | 2,550 | 09:February-23:February | |
| SHN Cluster Husum Nord | TenneT DE | negative | 185 | 2,550 | 09:February-23:February | |
| SHN Cluster Heide West T411 T412 | TenneT DE | negative | 178 | 2,450 | 09:February-23:February | |
| Schwarze Pumpe (Standort) | 50Hertz | Konventionell | negative | 260 | 2,342 | 06:February-15:February |
| Emsland Block C | Amprion | Konventionell | positive | 185 | 2,309 | 10:February-23:February |
| Emsland Block D | Amprion | Konventionell | positive | 451 | 2,256 | 23:February-04:February |
| WALSUM_10 | Amprion | Konventionell | negative | 226 | 2,035 | 06:February-16:February |
| UW Dörpen-West | TenneT DE | negative | 303 | 1,818 | 23:February-05:February | |
| AVA Cluster Voslapp | TenneT DE | negative | 302 | 1,812 | 23:February-05:February | |
| SHN Cluster Handewitt T414 T415 | TenneT DE | negative | 187 | 1,775 | 06:February-15:February | |
| Heizkraftwerk Heilbronn Block 7 | TransnetBW | Konventionell | positive | 231 | 1,731 | 23:February-06:February |
| UW Büttel | TenneT DE | negative | 423 | 1,692 | 19:February-23:February | |
| Börse | TenneT DE | Sonstiges | negative | 192 | 1,679 | 23:February-21:February |
| Irsching 5 | TenneT DE | Konventionell | negative | 224 | 1,570 | 05:February-12:February |
| Emsland Block D | Amprion | Konventionell | positive | 221 | 1,550 | 06:February-14:February |
| UW Dörpen-West | TenneT DE | negative | 159 | 1,506 | 05:February-15:February | |
| Jänschwalde (Standort) | 50Hertz | Konventionell | negative | 250 | 1,503 | 06:February-12:February |
| Börse | TenneT DE | Sonstiges | negative | 240 | 1,442 | 13:February-19:February |
| UW Diele | TenneT DE | negative | 100 | 1,400 | 06:February-23:February | |
| Grosskraftwerk Mannheim Block 8 | TransnetBW | Konventionell | positive | 105 | 1,392 | 23:February-12:February |
| Börse | TransnetBW | Sonstiges | negative | 105 | 1,392 | 23:February-12:February |
| Knapsack 1 | Amprion | Konventionell | positive | 165 | 1,365 | 05:February-15:February |
| Boxberg (Standort) | 50Hertz | Konventionell | negative | 210 | 1,261 | 06:February-12:February |
| Heizkraftwerk Heilbronn Block 7 | TransnetBW | Konventionell | positive | 180 | 988 | 05:February-13:February |
| UW Büttel | TenneT DE | negative | 336 | 925 | 06:February-09:February | |
| 50H_EDIS_CR_GUE_Nord | 50Hertz | negative | 89 | 912 | 05:February-21:February | |
| SHN Cluster Heide West T413 | TenneT DE | negative | 158 | 907 | 08:February-14:February | |
| GUD_HERNE_6 | Amprion | Konventionell | negative | 112 | 897 | 10:February-21:February |
| Netzreservekraftwerk HERNE_4 | Amprion | Konventionell | positive | 100 | 800 | 12:February-20:February |
| 50H_EDIS_CR_PAS | 50Hertz | negative | 100 | 775 | 05:February-13:February | |
| Schwarze Pumpe (Standort) | 50Hertz | Konventionell | negative | 173 | 692 | 09:February-14:February |
| Schkopau | 50Hertz | Konventionell | positive | 98 | 616 | 23:February-20:February |
| Irsching 5 | TenneT DE | Konventionell | positive | 115 | 603 | 23:February-04:February |
How BESS Can Reduce These Costs
Battery Energy Storage Systems at congestion points could have avoided an estimated €0.21M of today's redispatch costs by absorbing excess wind energy locally.
Learn BESS Arbitrage (Free) Stromfee AI PlatformFrequently Asked Questions
How much did redispatch cost on 2026-02-03?
On 2026-02-03, estimated redispatch costs were approximately €0.7 million. This includes €0.25M for renewable curtailment compensation and €0.31M for conventional ramp-up costs.
Which power plants were most affected on 2026-02-03?
The most affected plant was Börse (TenneT DE) with 23,389 MWh of positive redispatch.
What was the electricity spot price on 2026-02-03?
The EPEX Day-Ahead spot price for DE_LU ranged from 76 to 133 €/MWh with an average of 99 €/MWh.