2,429MWh Curtailed
2,427MWh Ramped Up
€0.65MEst. Cost
141 MWPeak Positive
Day-Ahead Spot: 74-154 €/MWh (avg 106)
TSO Breakdown
| TSO | Direction | Measures | Total MWh |
|---|---|---|---|
| TransnetBW | positive | 24 | 15,403 |
| TenneT DE | positive | 9 | 14,741 |
| TenneT DE | negative | 15 | 12,320 |
| 50Hertz | negative | 13 | 6,053 |
| Amprion | negative | 12 | 5,337 |
| Amprion | positive | 2 | 1,642 |
| 50Hertz | positive | 7 | 567 |
| TransnetBW | negative | 4 | 233 |
Plant-Level Redispatch Measures
| Plant | TSO | Fuel | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|---|
| Börse | TenneT DE | Sonstiges | positive | 435 | 6,530 | 00:January-23:January |
| Börse | TenneT DE | Sonstiges | positive | 850 | 5,100 | 23:January-05:January |
| Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 | TransnetBW | Konventionell | positive | 426 | 3,086 | 23:January-06:January |
| Wilhelmshaven (ENGIE) | TenneT DE | Konventionell | negative | 234 | 2,919 | 03:January-16:January |
| Heizkraftwerk Heilbronn Block 7 | TransnetBW | Konventionell | positive | 370 | 2,774 | 23:January-06:January |
| Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 | TransnetBW | Konventionell | positive | 221 | 2,206 | 23:January-09:January |
| SHN Cluster Heide West T411 T412 | TenneT DE | negative | 350 | 2,100 | 23:January-05:January | |
| Wilhelmshaven (ENGIE) | TenneT DE | Konventionell | negative | 272 | 1,973 | 13:January-21:January |
| Schwarze Pumpe (Standort) | 50Hertz | Konventionell | negative | 220 | 1,759 | 23:January-08:January |
| Wilhelmshaven (ENGIE) | TenneT DE | Konventionell | negative | 160 | 1,436 | 23:January-08:January |
| Gebersdorf 2 | TenneT DE | Konventionell | positive | 181 | 1,405 | 14:January-22:January |
| Datteln_4 | Amprion | Konventionell | negative | 224 | 1,344 | 23:January-05:January |
| UW Büttel | TenneT DE | negative | 128 | 1,308 | 05:January-23:January | |
| Emsland Block C | Amprion | Konventionell | positive | 168 | 1,222 | 14:January-23:January |
| Goldisthal (Standort) | 50Hertz | Sonstiges | negative | 550 | 1,100 | 09:January-11:January |
| Heizkraftwerk Heilbronn Block 7 | TransnetBW | Konventionell | positive | 270 | 1,080 | 19:January-23:January |
| Wilhelmshaven (ENGIE) | TenneT DE | Konventionell | negative | 100 | 1,051 | 11:January-23:January |
| Grosskraftwerk Mannheim Block 8 | TransnetBW | Konventionell | positive | 200 | 1,050 | 14:January-19:January |
| Lippendorf | 50Hertz | Konventionell | negative | 254 | 1,014 | 19:January-23:January |
| Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 | TransnetBW | Konventionell | positive | 218 | 874 | 17:January-21:January |
| Knapsack 1 | Amprion | Konventionell | negative | 187 | 748 | 04:January-19:January |
| KNAPSACK_20 | Amprion | Konventionell | negative | 144 | 719 | 14:January-19:January |
| NIEHL-31-GUD | Amprion | Konventionell | negative | 170 | 679 | 15:January-22:January |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 135 | 641 | 05:January-17:January |
| Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 | TransnetBW | Konventionell | positive | 103 | 619 | 14:January-23:January |
| Kiel (Küstenkraftwerk gesamt) | TenneT DE | Konventionell | negative | 90 | 608 | 16:January-22:January |
| Gebersdorf 2 | TenneT DE | Konventionell | positive | 137 | 584 | 14:January-18:January |
| Goldisthal (Standort) | 50Hertz | Sonstiges | negative | 255 | 574 | 14:January-17:January |
| Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 | TransnetBW | Konventionell | positive | 143 | 574 | 15:January-19:January |
| SW München KW-Pool | TenneT DE | Sonstiges | positive | 74 | 556 | 11:January-19:January |
| Boxberg (Standort) | 50Hertz | Konventionell | negative | 104 | 520 | 23:January-06:January |
| HAMMUENTROP_20 | Amprion | Konventionell | negative | 92 | 460 | 06:January-11:January |
| Heizkraftwerk Heilbronn Block 7 | TransnetBW | Konventionell | positive | 94 | 424 | 05:January-22:January |
| Emsland Block C | Amprion | Konventionell | positive | 210 | 420 | 21:January-23:January |
| NEURATH_G | Amprion | Konventionell | negative | 128 | 385 | 20:January-23:January |
| SHN Cluster Heide West T411 T412 | TenneT DE | negative | 182 | 364 | 15:January-17:January | |
| NIEHL-31-GUD | Amprion | Konventionell | negative | 109 | 326 | 23:January-02:January |
| Grosskraftwerk Mannheim Block 9 | TransnetBW | Konventionell | positive | 130 | 325 | 20:January-23:January |
| Heizkraftwerk Altbach/Deizisau Block 2 | TransnetBW | Konventionell | positive | 91 | 272 | 23:January-02:January |
| 50H Berlin Marzahn | 50Hertz | Konventionell | negative | 30 | 241 | 02:January-23:January |
| Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 | TransnetBW | Konventionell | positive | 94 | 212 | 08:January-11:January |
| Robert Frank 4 GT (KapRes) | TenneT DE | Konventionell | positive | 30 | 210 | 16:January-23:January |
| illwerke vkw AG | TransnetBW | Sonstiges | negative | 138 | 208 | 13:January-16:January |
| NIEHL-31-GUD | Amprion | Konventionell | negative | 102 | 204 | 18:January-20:January |
| Grosskraftwerk Mannheim Block 8 | TransnetBW | Konventionell | positive | 100 | 200 | 23:January-01:January |
| Jänschwalde (Standort) | 50Hertz | Konventionell | negative | 200 | 200 | 13:January-14:January |
| Kiel (Küstenkraftwerk gesamt) | TenneT DE | Konventionell | negative | 32 | 197 | 23:January-11:January |
| Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 | TransnetBW | Konventionell | positive | 92 | 184 | 20:January-22:January |
| SW München KW-Pool | TenneT DE | Sonstiges | positive | 84 | 168 | 09:January-11:January |
| NIEDERAUSSEM_G | Amprion | Konventionell | negative | 52 | 157 | 16:January-19:January |
How BESS Can Reduce These Costs
Battery Energy Storage Systems at congestion points could have avoided an estimated €0.2M of today's redispatch costs by absorbing excess wind energy locally.
Learn BESS Arbitrage (Free) Stromfee AI PlatformFrequently Asked Questions
How much did redispatch cost on 2026-01-13?
On 2026-01-13, estimated redispatch costs were approximately €0.65 million. This includes €0.24M for renewable curtailment compensation and €0.33M for conventional ramp-up costs.
Which power plants were most affected on 2026-01-13?
The most affected plant was Börse (TenneT DE) with 6,530 MWh of positive redispatch.
What was the electricity spot price on 2026-01-13?
The EPEX Day-Ahead spot price for DE_LU ranged from 74 to 154 €/MWh with an average of 106 €/MWh.