2,944MWh Curtailed
3,061MWh Ramped Up
€1.04MEst. Cost
190 MWPeak Positive
Day-Ahead Spot: 84-190 €/MWh (avg 127)
TSO Breakdown
| TSO | Direction | Measures | Total MWh |
|---|---|---|---|
| TenneT DE | positive | 4 | 28,093 |
| TransnetBW | positive | 12 | 23,910 |
| Amprion | negative | 14 | 14,451 |
| TenneT DE | negative | 7 | 8,770 |
| 50Hertz | positive | 7 | 3,101 |
| 50Hertz | negative | 2 | 1,765 |
| TransnetBW | negative | 1 | 62 |
Plant-Level Redispatch Measures
| Plant | TSO | Fuel | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|---|
| Börse | TenneT DE | Sonstiges | positive | 1020 | 23,455 | 23:January-23:January |
| Heizkraftwerk Heilbronn Block 7 | TransnetBW | Konventionell | positive | 677 | 16,238 | 23:January-23:January |
| Gebersdorf 2 | TenneT DE | Konventionell | positive | 263 | 3,414 | 23:January-23:January |
| NIEDERAUSSEM_K | Amprion | Konventionell | negative | 405 | 3,243 | 23:January-07:January |
| Knapsack 1 | Amprion | Konventionell | negative | 264 | 2,707 | 23:January-23:January |
| UW Büttel | TenneT DE | negative | 432 | 2,594 | 23:January-05:January | |
| HAMMUENTROP_20 | Amprion | Konventionell | negative | 156 | 2,177 | 23:January-15:January |
| KNAPSACK_20 | Amprion | Konventionell | negative | 169 | 1,906 | 23:January-23:January |
| Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 | TransnetBW | Konventionell | positive | 300 | 1,800 | 17:January-23:January |
| Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 | TransnetBW | Konventionell | positive | 220 | 1,760 | 23:January-07:January |
| UW Büttel | TenneT DE | negative | 462 | 1,616 | 18:January-23:January | |
| Jänschwalde (Standort) | 50Hertz | Konventionell | positive | 227 | 1,592 | 23:January-06:January |
| 50H Hamburg Wedel1 | 50Hertz | Konventionell | negative | 61 | 1,453 | 23:January-23:January |
| Heizkraftwerk Altbach/Deizisau Block 2 | TransnetBW | Konventionell | positive | 132 | 1,418 | 23:January-12:January |
| Kiel (Küstenkraftwerk gesamt) | TenneT DE | Konventionell | negative | 73 | 1,389 | 23:January-19:January |
| Heizkraftwerk Heilbronn Block 7 | TransnetBW | Konventionell | positive | 404 | 1,312 | 19:January-23:January |
| Wilhelmshaven (ENGIE) | TenneT DE | Konventionell | negative | 230 | 1,265 | 17:January-23:January |
| Gebersdorf 2 | TenneT DE | Konventionell | positive | 366 | 1,189 | 19:January-23:January |
| Wilhelmshaven (ENGIE) | TenneT DE | Konventionell | negative | 258 | 1,030 | 23:January-03:January |
| NIEHL-31-GUD | Amprion | Konventionell | negative | 136 | 955 | 23:January-06:January |
| Grosskraftwerk Mannheim Block 8 | TransnetBW | Konventionell | positive | 92 | 915 | 23:January-09:January |
| Schkopau | 50Hertz | Konventionell | positive | 137 | 821 | 23:January-05:January |
| Emsland Block D | Amprion | Konventionell | negative | 264 | 793 | 20:January-23:January |
| NIEHL-II | Amprion | Konventionell | negative | 103 | 718 | 23:January-06:January |
| Wilhelmshaven (ENGIE) | TenneT DE | Konventionell | negative | 155 | 620 | 19:January-23:January |
| Knapsack 1 | Amprion | Konventionell | negative | 210 | 420 | 21:January-23:January |
| NIEHL-31-GUD | Amprion | Konventionell | negative | 210 | 419 | 21:January-23:January |
| HAMMUENTROP_20 | Amprion | Konventionell | negative | 130 | 389 | 20:January-23:January |
| KNAPSACK_20 | Amprion | Konventionell | negative | 125 | 375 | 20:January-23:January |
| 50H Hamburg Tiefstack GuD | 50Hertz | Konventionell | positive | 55 | 330 | 23:January-23:January |
| 50H Hamburg Wedel1 | 50Hertz | Konventionell | negative | 62 | 312 | 18:January-23:January |
| Kiel (Küstenkraftwerk gesamt) | TenneT DE | Konventionell | negative | 64 | 255 | 18:January-22:January |
| NIEHL-31-GUD | Amprion | Konventionell | negative | 100 | 225 | 18:January-21:January |
| Heizkraftwerk Altbach/Deizisau Block 2 | TransnetBW | Konventionell | positive | 165 | 165 | 22:January-23:January |
| 50H Hamburg Tiefstack GuD | 50Hertz | Konventionell | positive | 53 | 159 | 20:January-23:January |
| Jänschwalde (Standort) | 50Hertz | Konventionell | positive | 72 | 145 | 21:January-23:January |
| WALSUM_10 | Amprion | Konventionell | negative | 50 | 112 | 20:January-22:January |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 85 | 85 | 23:January-00:January |
| Börse | TransnetBW | Sonstiges | positive | 39 | 78 | 18:January-22:January |
| Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 | TransnetBW | Konventionell | positive | 31 | 69 | 20:January-23:January |
| Börse | TransnetBW | Sonstiges | negative | 41 | 62 | 17:January-18:January |
| Grosskraftwerk Mannheim Block 9 | TransnetBW | Konventionell | positive | 45 | 45 | 22:January-23:January |
| Eltmann | TenneT DE | Konventionell | positive | 35 | 35 | 22:January-23:January |
| Börse | 50Hertz | Sonstiges | positive | 15 | 34 | 23:January-05:January |
| Grosskraftwerk Mannheim Block 8 | TransnetBW | Konventionell | positive | 10 | 26 | 18:January-20:January |
| 50H Berlin Lichterfelde | 50Hertz | Konventionell | positive | 10 | 20 | 21:January-23:January |
| Börse | Amprion | Konventionell | negative | 50 | 12 | 22:January-22:January |
How BESS Can Reduce These Costs
Battery Energy Storage Systems at congestion points could have avoided an estimated €0.31M of today's redispatch costs by absorbing excess wind energy locally.
Learn BESS Arbitrage (Free) Stromfee AI PlatformFrequently Asked Questions
How much did redispatch cost on 2026-01-06?
On 2026-01-06, estimated redispatch costs were approximately €1.04 million. This includes €0.29M for renewable curtailment compensation and €0.48M for conventional ramp-up costs.
Which power plants were most affected on 2026-01-06?
The most affected plant was Börse (TenneT DE) with 23,455 MWh of positive redispatch.
What was the electricity spot price on 2026-01-06?
The EPEX Day-Ahead spot price for DE_LU ranged from 84 to 190 €/MWh with an average of 127 €/MWh.