← 2026-10-10

Sunday, October 11, 2026

2026-10-12 →
3,224MWh Curtailed
3,147MWh Ramped Up
€1.12MEst. Cost
246 MWPeak Positive

Day-Ahead Spot: 14-242 €/MWh (avg 128)

TSO Breakdown

TSODirectionMeasuresTotal MWh
Amprion negative 5 3,790
Amprion positive 2 3,452
TenneT DE positive 2 3,432
TenneT DE negative 7 1,091
50Hertz negative 6 846
TransnetBW positive 1 640
50Hertz positive 1 5

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
Emsland Block D Amprion Konventionell positive 353 2,822 00:October-08:October
Irsching 4 TenneT DE Konventionell positive 266 2,126 14:October-22:October
NIEDERAUSSEM_H Amprion Konventionell negative 298 2,084 15:October-22:October
Irsching 4 TenneT DE Konventionell positive 307 1,306 22:October-02:October
NIEDERAUSSEM_H Amprion Konventionell negative 222 1,000 22:October-02:October
Grosskraftwerk Mannheim Block 6 TransnetBW Konventionell positive 40 640 00:October-16:October
Emsland Block B Amprion Konventionell positive 210 630 00:October-03:October
AVA Cluster Helmstedt TenneT DE Erneuerbar negative 150 412 12:October-15:October
SHN Cluster Süderdonn T412 T413 TenneT DE Erneuerbar negative 120 300 05:October-08:October
NIEDERAUSSEM_G Amprion Konventionell negative 79 296 22:October-01:October
AVA Cluster Conneforde TenneT DE Erneuerbar negative 178 267 04:October-06:October
50H Berlin Mitte 50Hertz Konventionell negative 120 239 05:October-07:October
NIEDERAUSSEM_G Amprion Konventionell negative 134 235 07:October-08:October
50H Dresden-Reick 50Hertz Konventionell negative 44 220 03:October-08:October
NIEDERAUSSEM_G Amprion Konventionell negative 58 175 04:October-07:October
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 152 152 04:October-05:October
50H_EDIS_CR_WU_NORD 50Hertz Erneuerbar negative 50 112 11:October-14:October
SHN Cluster Baltic Cable TenneT DE Erneuerbar negative 69 87 07:October-08:October
50H Dresden-Nossen 50Hertz Konventionell negative 21 64 03:October-06:October
50H Berlin Mitte 50Hertz Konventionell negative 59 59 04:October-05:October
UW Diele TenneT DE Erneuerbar negative 1 8 04:October-13:October
UW Dörpen-West TenneT DE Erneuerbar negative 1 8 04:October-13:October
UW Emden-Ost TenneT DE Erneuerbar negative 1 8 04:October-13:October
50H Dresden-Reick 50Hertz Konventionell positive 5 5 08:October-09:October

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.34M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-10-11?

On 2026-10-11, estimated redispatch costs were approximately €1.12 million. This includes €0.32M for renewable curtailment compensation and €0.5M for conventional ramp-up costs.

Which power plants were most affected on 2026-10-11?

The most affected plant was Emsland Block D (Amprion) with 2,822 MWh of positive redispatch.

What was the electricity spot price on 2026-10-11?

The EPEX Day-Ahead spot price for DE_LU ranged from 14 to 242 €/MWh with an average of 128 €/MWh.