← 2026-02-23

Tuesday, February 24, 2026

2026-02-25 →
2,626MWh Curtailed
2,163MWh Ramped Up
€0.66MEst. Cost
182 MWPeak Positive

Day-Ahead Spot: 78-186 €/MWh (avg 115)

TSO Breakdown

TSODirectionMeasuresTotal MWh
TransnetBW positive 4 4,860
TenneT DE positive 2 2,560
Amprion negative 6 2,284
Amprion positive 3 2,117
TenneT DE negative 1 1,272
50Hertz negative 1 4

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 TransnetBW Konventionell positive 270 4,392 03:February-20:February
ReserveKW Zolling 5 TenneT DE Konventionell positive 215 2,530 04:February-15:February
Emsland Block D Amprion Konventionell negative 238 1,962 03:February-16:February
Netzreservekraftwerk Bexbach A Amprion Konventionell positive 234 1,402 14:February-20:February
Börse TenneT DE Sonstiges negative 124 1,272 04:February-15:February
WEISWEILERVGT_H3 Amprion Konventionell positive 154 540 04:February-08:February
illwerke vkw AG TransnetBW Sonstiges positive 161 322 05:February-07:February
Börse Amprion Konventionell positive 64 175 05:February-17:February
Börse Amprion Konventionell negative 250 125 20:February-20:February
Reservekraftwerk Marbach GT 3 TransnetBW Konventionell positive 63 110 06:February-08:February
CHEMIEPARK_MARL_KRAFTWERKE Amprion Konventionell negative 39 79 04:February-16:February
NIEHL-31-GUD Amprion Konventionell negative 37 46 04:February-16:February
WALSUM_10 Amprion Konventionell negative 80 40 04:February-05:February
Heizkraftwerk Altbach/Deizisau GT E TransnetBW Konventionell positive 70 35 06:February-06:February
Datteln_4 Amprion Konventionell negative 65 32 04:February-05:February
Börse TenneT DE Sonstiges positive 60 30 08:February-08:February
Börse 50Hertz Sonstiges negative 6 4 09:February-10:February

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.2M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-02-24?

On 2026-02-24, estimated redispatch costs were approximately €0.66 million. This includes €0.26M for renewable curtailment compensation and €0.31M for conventional ramp-up costs.

Which power plants were most affected on 2026-02-24?

The most affected plant was Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 (TransnetBW) with 4,392 MWh of positive redispatch.

What was the electricity spot price on 2026-02-24?

The EPEX Day-Ahead spot price for DE_LU ranged from 78 to 186 €/MWh with an average of 115 €/MWh.