← 2026-01-28

Thursday, January 29, 2026

2026-01-30 →
2,921MWh Curtailed
3,148MWh Ramped Up
€1MEst. Cost
173 MWPeak Positive

Day-Ahead Spot: 96-173 €/MWh (avg 133)

TSO Breakdown

TSODirectionMeasuresTotal MWh
Amprion positive 19 31,705
TenneT DE positive 5 30,742
TenneT DE negative 12 29,627
TransnetBW positive 14 24,820
50Hertz negative 12 5,389
50Hertz positive 3 484
Amprion negative 1 392
TransnetBW negative 1 5

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
Börse TenneT DE Sonstiges positive 1100 26,400 23:January-23:January
Wilhelmshaven (ENGIE) TenneT DE Konventionell negative 623 14,950 23:January-23:January
Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 TransnetBW Konventionell positive 383 9,188 23:January-23:January
Heizkraftwerk Heilbronn Block 7 TransnetBW Konventionell positive 367 8,800 23:January-23:January
UW Büttel TenneT DE Erneuerbar negative 508 7,750 05:January-23:January
Emsland Block D Amprion Konventionell positive 427 6,938 23:January-15:January
Netzreservekraftwerk BERGKAMEN_A Amprion Konventionell positive 388 6,589 06:January-23:January
Emsland Block B Amprion Konventionell positive 274 4,588 04:January-21:January
Netzreservekraftwerk Bexbach A Amprion Konventionell positive 310 4,422 05:January-20:January
ReserveKW Ingolstadt 3 TenneT DE Konventionell positive 204 3,368 05:January-21:January
GERSTEINW_G (KapRes) Amprion Konventionell positive 140 2,443 03:January-21:January
ReserveKW Ingolstadt 3 TenneT DE Konventionell negative 134 2,212 05:January-21:January
UW Büttel TenneT DE Erneuerbar negative 341 2,134 23:January-06:January
Grosskraftwerk Mannheim Block 8 TransnetBW Konventionell positive 181 2,122 23:January-22:January
50H Berlin Marzahn 50Hertz Konventionell negative 111 1,466 07:January-21:January
Emsland Block C Amprion Konventionell positive 280 1,400 13:January-22:January
illwerke vkw AG TransnetBW Sonstiges positive 190 1,233 13:January-23:January
Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 TransnetBW Konventionell positive 291 1,165 19:January-23:January
Netzreservekraftwerk Bexbach A Amprion Konventionell positive 125 1,155 10:January-19:January
50H Berlin Mitte 50Hertz Konventionell negative 77 1,133 06:January-21:January
Netzreservekraftwerk GTKW-DA-POOL Amprion Konventionell positive 86 1,118 07:January-20:January
Emsland Block D Amprion Konventionell positive 623 1,090 20:January-22:January
GERSTEINW_G (KapRes) Amprion Konventionell positive 137 991 09:January-18:January
Kiel (Küstenkraftwerk gesamt) TenneT DE Konventionell negative 60 954 06:January-22:January
Gebersdorf GT TenneT DE Konventionell positive 54 870 04:January-20:January
SHN Cluster Handewitt T414 T415 TenneT DE Erneuerbar negative 188 750 19:January-23:January
50H Hamburg Wedel1 50Hertz Konventionell negative 38 715 04:January-23:January
Grosskraftwerk Mannheim Block 8 TransnetBW Konventionell positive 180 676 19:January-23:January
Boxberg (Standort) 50Hertz Konventionell negative 78 583 05:January-20:January
UW Büttel TenneT DE Erneuerbar negative 290 580 21:January-23:January
Heizkraftwerk Heilbronn Block 7 TransnetBW Konventionell positive 165 576 04:January-21:January
illwerke vkw AG TransnetBW Sonstiges positive 29 410 23:January-23:January
Knapsack 1 Amprion Konventionell negative 131 392 20:January-23:January
50H Berlin Marzahn 50Hertz Konventionell negative 56 390 06:January-13:January
Schkopau 50Hertz Konventionell positive 125 374 03:January-23:January
Boxberg (Standort) 50Hertz Konventionell negative 109 326 10:January-13:January
50H Berlin Lichterfelde 50Hertz Konventionell negative 49 282 15:January-20:January
Rostock Kohlekraftwerk 50Hertz Konventionell negative 84 252 03:January-23:January
Netzreservekraftwerk BERGKAMEN_A Amprion Konventionell positive 49 197 12:January-19:January
Heizkraftwerk Heilbronn Block 7 TransnetBW Konventionell positive 138 172 20:January-21:January
Pumpspeicherwerk Säckingen RZ TNG TransnetBW Sonstiges positive 85 170 11:January-13:January
Rostock Kohlekraftwerk 50Hertz Konventionell negative 72 144 23:January-05:January
Heizkraftwerk Altbach/Deizisau Block 2 TransnetBW Konventionell positive 114 142 23:January-00:January
Emsland Block C Amprion Konventionell positive 70 140 18:January-20:January
Emsland Block B Amprion Konventionell positive 108 134 06:January-07:January
Emsland Block C Amprion Konventionell positive 130 130 12:January-13:January
Emsland Block D Amprion Konventionell positive 245 122 22:January-23:January
Börse Amprion Konventionell positive 153 115 05:January-07:January
UW Dörpen-West TenneT DE Erneuerbar negative 105 105 22:January-23:January
Heizkraftwerk Heilbronn Block 7 TransnetBW Konventionell positive 150 75 22:January-23:January

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.3M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-01-29?

On 2026-01-29, estimated redispatch costs were approximately €1 million. This includes €0.29M for renewable curtailment compensation and €0.51M for conventional ramp-up costs.

Which power plants were most affected on 2026-01-29?

The most affected plant was Börse (TenneT DE) with 26,400 MWh of positive redispatch.

What was the electricity spot price on 2026-01-29?

The EPEX Day-Ahead spot price for DE_LU ranged from 96 to 173 €/MWh with an average of 133 €/MWh.