Netzreservekraftwerk VOELKLINGEN_HKV

KonventionellAmprion

17,001Total MWh
14Measures
85 MWAvg Power
0Curtailments
14Ramp-ups

Data: 2024-03-11 to 2026-05-11

Daily Redispatch Volume

DateMeasuresTotal MWh
2026-05-11 1 930
2026-05-07 1 896
2026-05-04 1 12
2026-04-28 1 678
2026-04-27 1 485
2025-02-19 2 3,324
2025-01-27 2 1,569
2024-03-14 1 112
2024-03-13 1 2,168
2024-03-12 1 2,536
2024-03-11 2 4,291

Recent Measures

DateTSODirAvg MWMWhTime
2026-05-11 Amprion positive 128 930 08:May-15:May
2026-05-07 Amprion positive 102 896 05:May-16:May
2026-05-04 Amprion positive 25 12 08:May-08:May
2026-04-28 Amprion positive 90 678 07:April-14:April
2026-04-27 Amprion positive 65 485 08:April-16:April
2025-02-19 Amprion positive 98 1,965 23:February-19:February
2025-02-19 Amprion positive 95 1,359 08:February-23:February
2025-01-27 Amprion positive 78 1,234 23:January-14:January
2025-01-27 Amprion positive 52 335 11:January-23:January
2024-03-14 Amprion positive 38 112 06:March-09:March
2024-03-13 Amprion positive 117 2,168 23:March-17:March
2024-03-12 Amprion positive 106 2,536 23:March-23:March
2024-03-11 Amprion positive 106 2,536 23:March-23:March
2024-03-11 Amprion positive 95 1,755 02:March-23:March

Frequently Asked Questions

What is the redispatch history of Netzreservekraftwerk VOELKLINGEN_HKV?

Netzreservekraftwerk VOELKLINGEN_HKV is a Konventionell power plant in the Amprion grid zone. It has received 14 redispatch instructions totaling 17,001 MWh since 2024-03-11.

Why is Netzreservekraftwerk VOELKLINGEN_HKV frequently redispatched?

Plants in the Amprion zone are frequently ramped up to compensate for curtailed renewables in Northern Germany. This is part of Germany's structural North-South grid bottleneck.