50H_EDIS_CR_BW
• 50Hertz
8,265Total MWh
13Measures
98 MWAvg Power
13Curtailments
0Ramp-ups
Data: 2024-05-01 to 2026-05-04
Daily Redispatch Volume
| Date | Measures | Total MWh |
|---|---|---|
| 2026-05-04 | 1 | 478 |
| 2026-05-03 | 1 | 136 |
| 2026-04-26 | 1 | 75 |
| 2026-04-22 | 2 | 312 |
| 2026-04-20 | 4 | 6,186 |
| 2025-09-27 | 1 | 200 |
| 2024-07-21 | 1 | 80 |
| 2024-05-21 | 1 | 360 |
| 2024-05-01 | 1 | 438 |
Recent Measures
| Date | TSO | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|
| 2026-05-04 | 50Hertz | negative | 87 | 478 | 07:May-13:May |
| 2026-05-03 | 50Hertz | negative | 36 | 136 | 07:May-10:May |
| 2026-04-26 | 50Hertz | negative | 50 | 75 | 07:April-09:April |
| 2026-04-22 | 50Hertz | negative | 78 | 156 | 06:April-08:April |
| 2026-04-22 | 50Hertz | negative | 78 | 156 | 06:April-08:April |
| 2026-04-20 | 50Hertz | negative | 18 | 18 | 11:April-12:April |
| 2026-04-20 | 50Hertz | negative | 18 | 18 | 11:April-12:April |
| 2026-04-20 | 50Hertz | negative | 293 | 3,075 | 07:April-18:April |
| 2026-04-20 | 50Hertz | negative | 293 | 3,075 | 07:April-18:April |
| 2025-09-27 | 50Hertz | negative | 100 | 200 | 10:September-12:September |
| 2024-07-21 | 50Hertz | negative | 40 | 80 | 10:July-12:July |
| 2024-05-21 | 50Hertz | negative | 80 | 360 | 09:May-13:May |
| 2024-05-01 | 50Hertz | negative | 97 | 438 | 08:May-13:May |
Frequently Asked Questions
What is the redispatch history of 50H_EDIS_CR_BW?
50H_EDIS_CR_BW is a Erneuerbar power plant in the 50Hertz grid zone. It has received 13 redispatch instructions totaling 8,265 MWh since 2024-05-01.
Why is 50H_EDIS_CR_BW frequently redispatched?
Plants in the 50Hertz zone are frequently curtailed due to grid congestion from excess renewable generation in Northern Germany. This is part of Germany's structural North-South grid bottleneck.