← 2026-06-28

Monday, June 29, 2026

2026-06-30 →
2,647MWh Curtailed
3,760MWh Ramped Up
€1.13MEst. Cost
484 MWPeak Positive

Day-Ahead Spot: 77-342 €/MWh (avg 142)

TSO Breakdown

TSODirectionMeasuresTotal MWh
TenneT DE negative 8 6,498
Amprion negative 10 804
Amprion positive 2 104
50Hertz positive 2 60
TransnetBW positive 2 34
TransnetBW negative 2 28

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
BAG NWAK-Cluster 15 Pleinting TenneT DE Erneuerbar negative 280 2,100 08:June-16:June
BAG NWAK-Cluster 15 Pleinting TenneT DE Erneuerbar negative 280 2,100 08:June-16:June
BAG NWAK-Cluster 17 Altheim TenneT DE Erneuerbar negative 100 750 08:June-16:June
BAG NWAK-Cluster 17 Altheim TenneT DE Erneuerbar negative 100 750 08:June-16:June
BAG NWAK-Cluster 16 Regensburg-Sittling TenneT DE Erneuerbar negative 50 375 08:June-16:June
BAG NWAK-Cluster 16 Regensburg-Sittling TenneT DE Erneuerbar negative 50 375 08:June-16:June
HAMMUENTROP_20 Amprion Konventionell negative 124 155 15:June-16:June
HAMMUENTROP_20 Amprion Konventionell negative 124 155 15:June-16:June
GUD_HERNE_6 Amprion Konventionell negative 121 121 15:June-16:June
GUD_HERNE_6 Amprion Konventionell negative 121 121 15:June-16:June
WALSUM_10 Amprion Konventionell negative 82 102 14:June-16:June
WALSUM_10 Amprion Konventionell negative 82 102 14:June-16:June
BIBLIS_GT (bnBm) Amprion Konventionell positive 14 52 08:June-15:June
BIBLIS_GT (bnBm) Amprion Konventionell positive 14 52 08:June-15:June
Börse 50Hertz Sonstiges positive 15 30 16:June-18:June
Börse 50Hertz Sonstiges positive 15 30 16:June-18:June
Eltmann TenneT DE Konventionell negative 24 24 15:June-16:June
Eltmann TenneT DE Konventionell negative 24 24 15:June-16:June
Börse TransnetBW Sonstiges positive 34 17 14:June-16:June
Börse TransnetBW Sonstiges positive 34 17 14:June-16:June
Börse TransnetBW Sonstiges negative 57 14 15:June-15:June
Börse TransnetBW Sonstiges negative 57 14 15:June-15:June
KMW_KW3 Amprion Konventionell negative 12 12 12:June-13:June
GUD_HERNE_6 Amprion Konventionell negative 12 12 13:June-15:June
KMW_KW3 Amprion Konventionell negative 12 12 12:June-13:June
GUD_HERNE_6 Amprion Konventionell negative 12 12 13:June-15:June

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.34M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-06-29?

On 2026-06-29, estimated redispatch costs were approximately €1.13 million. This includes €0.26M for renewable curtailment compensation and €0.65M for conventional ramp-up costs.

Which power plants were most affected on 2026-06-29?

The most affected plant was BAG NWAK-Cluster 15 Pleinting (TenneT DE) with 2,100 MWh of negative redispatch.

What was the electricity spot price on 2026-06-29?

The EPEX Day-Ahead spot price for DE_LU ranged from 77 to 342 €/MWh with an average of 142 €/MWh.