2,448MWh Curtailed
2,662MWh Ramped Up
€0.91MEst. Cost
153 MWPeak Positive
Day-Ahead Spot: 96-146 €/MWh (avg 109)
TSO Breakdown
| TSO | Direction | Measures | Total MWh |
|---|---|---|---|
| Amprion | negative | 5 | 15,221 |
| Amprion | positive | 3 | 13,877 |
| 50Hertz | negative | 24 | 13,762 |
| TransnetBW | positive | 16 | 13,717 |
| TenneT DE | positive | 2 | 10,237 |
| TenneT DE | negative | 6 | 2,926 |
| TransnetBW | negative | 1 | 21 |
Plant-Level Redispatch Measures
| Plant | TSO | Fuel | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|---|
| Börse | Amprion | Konventionell | negative | 494 | 11,845 | 23:January-23:January |
| Netzreservekraftwerk BERGKAMEN_A | Amprion | Konventionell | positive | 494 | 11,845 | 23:January-23:January |
| Börse | TenneT DE | Sonstiges | positive | 796 | 5,570 | 08:January-23:January |
| Börse | TenneT DE | Sonstiges | positive | 778 | 4,667 | 23:January-05:January |
| Reservekraftwerk Altbach/Deizisau Block 1 | TransnetBW | Konventionell | positive | 260 | 3,900 | 08:January-23:January |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 495 | 1,980 | 10:January-14:January |
| Schkopau | 50Hertz | Konventionell | negative | 159 | 1,913 | 09:January-23:January |
| Börse | Amprion | Konventionell | negative | 271 | 1,898 | 16:January-23:January |
| Netzreservekraftwerk BERGKAMEN_A | Amprion | Konventionell | positive | 271 | 1,898 | 16:January-23:January |
| 50H Berlin Marzahn | 50Hertz | Konventionell | negative | 131 | 1,828 | 09:January-23:January |
| UW Büttel | TenneT DE | negative | 359 | 1,618 | 04:January-09:January | |
| Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 | TransnetBW | Konventionell | positive | 268 | 1,608 | 23:January-05:January |
| Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 | TransnetBW | Konventionell | positive | 237 | 1,542 | 16:January-23:January |
| Lippendorf | 50Hertz | Konventionell | negative | 208 | 1,350 | 16:January-23:January |
| WALSUM_10 | Amprion | Konventionell | negative | 210 | 1,315 | 23:January-05:January |
| Lippendorf | 50Hertz | Konventionell | negative | 364 | 1,275 | 10:January-14:January |
| 50H Berlin Marzahn | 50Hertz | Konventionell | negative | 115 | 1,268 | 23:January-14:January |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 262 | 1,049 | 05:January-09:January |
| Reservekraftwerk Altbach/Deizisau Block 1 | TransnetBW | Konventionell | positive | 127 | 828 | 16:January-23:January |
| 50H Berlin Lichterfelde | 50Hertz | Konventionell | negative | 68 | 821 | 09:January-22:January |
| Lippendorf | 50Hertz | Konventionell | negative | 161 | 764 | 18:January-23:January |
| BAG NWAK-Cluster 15 Pleinting | TenneT DE | negative | 200 | 750 | 11:January-15:January | |
| Schkopau | 50Hertz | Konventionell | negative | 139 | 661 | 18:January-23:January |
| Grosskraftwerk Mannheim Block 8 | TransnetBW | Konventionell | positive | 65 | 650 | 13:January-23:January |
| 50H Erfurt-Ost HKW GuD | 50Hertz | Konventionell | negative | 43 | 605 | 09:January-23:January |
| Schkopau | 50Hertz | Konventionell | negative | 171 | 600 | 10:January-14:January |
| Heizkraftwerk Altbach/Deizisau Block 2 | TransnetBW | Konventionell | positive | 126 | 569 | 04:January-09:January |
| 50H_AVA_CR_WOL | 50Hertz | negative | 150 | 488 | 10:January-14:January | |
| Heizkraftwerk Altbach/Deizisau Block 2 | TransnetBW | Konventionell | positive | 121 | 422 | 10:January-14:January |
| Schkopau | 50Hertz | Konventionell | negative | 205 | 410 | 23:January-01:January |
| BAG NWAK-Cluster 16 Regensburg-Sittling | TenneT DE | negative | 100 | 375 | 11:January-15:January | |
| 50H PV Witznitz | 50Hertz | negative | 113 | 310 | 10:January-12:January | |
| Reservekraftwerk Altbach/Deizisau Block 1 | TransnetBW | Konventionell | positive | 298 | 298 | 23:January-00:January |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 71 | 285 | 07:January-18:January |
| Heizkraftwerk Altbach/Deizisau Block 2 | TransnetBW | Konventionell | positive | 78 | 252 | 19:January-23:January |
| 50H Berlin Lichterfelde | 50Hertz | Konventionell | negative | 68 | 239 | 07:January-17:January |
| Reservekraftwerk Altbach/Deizisau Block 1 | TransnetBW | Konventionell | positive | 58 | 190 | 10:January-14:January |
| 50H_AVA_CR_STW | 50Hertz | negative | 50 | 162 | 10:January-14:January | |
| 50H UW Schönewalde | 50Hertz | negative | 91 | 158 | 10:January-12:January | |
| Lippendorf | 50Hertz | Konventionell | negative | 68 | 152 | 23:January-11:January |
| 50H OWP Baltic Eagle | 50Hertz | negative | 120 | 150 | 10:January-12:January | |
| Schkopau | 50Hertz | Konventionell | negative | 36 | 146 | 08:January-17:January |
| WALSUM_10 | Amprion | Konventionell | negative | 142 | 142 | 17:January-18:January |
| 50H Leipzig Nord GuD | 50Hertz | Konventionell | negative | 22 | 135 | 09:January-21:January |
| WEISWEILER_G | Amprion | Konventionell | positive | 67 | 134 | 23:January-01:January |
| 50H Halle-Dieselstr HKW-BlockB | 50Hertz | Konventionell | negative | 11 | 127 | 09:January-23:January |
| 50H OWP Arcadis Ost 1 | 50Hertz | negative | 82 | 103 | 10:January-12:January | |
| Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 | TransnetBW | Konventionell | positive | 76 | 95 | 21:January-23:January |
| Jänschwalde (Standort) | 50Hertz | Konventionell | negative | 46 | 92 | 18:January-21:January |
| Eltmann | TenneT DE | Konventionell | negative | 26 | 78 | 15:January-22:January |
How BESS Can Reduce These Costs
Battery Energy Storage Systems at congestion points could have avoided an estimated €0.27M of today's redispatch costs by absorbing excess wind energy locally.
Learn BESS Arbitrage (Free) Stromfee AI PlatformFrequently Asked Questions
How much did redispatch cost on 2026-01-18?
On 2026-01-18, estimated redispatch costs were approximately €0.91 million. This includes €0.24M for renewable curtailment compensation and €0.37M for conventional ramp-up costs.
Which power plants were most affected on 2026-01-18?
The most affected plant was Börse (Amprion) with 11,845 MWh of negative redispatch.
What was the electricity spot price on 2026-01-18?
The EPEX Day-Ahead spot price for DE_LU ranged from 96 to 146 €/MWh with an average of 109 €/MWh.