50H_EDIS_CR_ATS
• 50Hertz
4,699Total MWh
10Measures
105 MWAvg Power
10Curtailments
0Ramp-ups
Data: 2024-01-21 to 2026-05-03
Daily Redispatch Volume
| Date | Measures | Total MWh |
|---|---|---|
| 2026-05-03 | 1 | 388 |
| 2026-04-27 | 1 | 162 |
| 2026-04-22 | 2 | 224 |
| 2026-03-13 | 1 | 262 |
| 2024-06-22 | 1 | 250 |
| 2024-06-11 | 1 | 288 |
| 2024-05-17 | 1 | 500 |
| 2024-05-15 | 1 | 2,325 |
| 2024-01-21 | 1 | 300 |
Recent Measures
| Date | TSO | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|
| 2026-05-03 | 50Hertz | negative | 74 | 388 | 06:May-11:May |
| 2026-04-27 | 50Hertz | negative | 93 | 162 | 08:April-10:April |
| 2026-04-22 | 50Hertz | negative | 50 | 112 | 06:April-09:April |
| 2026-04-22 | 50Hertz | negative | 50 | 112 | 06:April-09:April |
| 2026-03-13 | 50Hertz | negative | 150 | 262 | 12:March-14:March |
| 2024-06-22 | 50Hertz | negative | 100 | 250 | 11:June-14:June |
| 2024-06-11 | 50Hertz | negative | 82 | 288 | 09:June-15:June |
| 2024-05-17 | 50Hertz | negative | 100 | 500 | 09:May-14:May |
| 2024-05-15 | 50Hertz | negative | 266 | 2,325 | 09:May-18:May |
| 2024-01-21 | 50Hertz | negative | 86 | 300 | 11:January-14:January |
Frequently Asked Questions
What is the redispatch history of 50H_EDIS_CR_ATS?
50H_EDIS_CR_ATS is a Erneuerbar power plant in the 50Hertz grid zone. It has received 10 redispatch instructions totaling 4,699 MWh since 2024-01-21.
Why is 50H_EDIS_CR_ATS frequently redispatched?
Plants in the 50Hertz zone are frequently curtailed due to grid congestion from excess renewable generation in Northern Germany. This is part of Germany's structural North-South grid bottleneck.