Obernburg
Konventionell • TenneT DE
135Total MWh
8Measures
6 MWAvg Power
4Curtailments
4Ramp-ups
Data: 2025-08-04 to 2026-02-20
Daily Redispatch Volume
| Date | Measures | Total MWh |
|---|---|---|
| 2026-02-20 | 1 | 9 |
| 2026-02-02 | 1 | 21 |
| 2025-12-28 | 1 | 7 |
| 2025-12-06 | 1 | 28 |
| 2025-09-09 | 1 | 28 |
| 2025-08-08 | 1 | 24 |
| 2025-08-07 | 1 | 8 |
| 2025-08-04 | 1 | 10 |
Recent Measures
| Date | TSO | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|
| 2026-02-20 | TenneT DE | negative | 1 | 9 | 23:February-08:February |
| 2026-02-02 | TenneT DE | negative | 7 | 21 | 04:February-07:February |
| 2025-12-28 | TenneT DE | positive | 7 | 7 | 22:December-23:December |
| 2025-12-06 | TenneT DE | negative | 7 | 28 | 14:December-18:December |
| 2025-09-09 | TenneT DE | positive | 7 | 28 | 07:September-11:September |
| 2025-08-08 | TenneT DE | positive | 8 | 24 | 08:August-11:August |
| 2025-08-07 | TenneT DE | positive | 8 | 8 | 08:August-09:August |
| 2025-08-04 | TenneT DE | negative | 2 | 10 | 09:August-14:August |
Frequently Asked Questions
What is the redispatch history of Obernburg?
Obernburg is a Konventionell power plant in the TenneT DE grid zone. It has received 8 redispatch instructions totaling 135 MWh since 2025-08-04.
Why is Obernburg frequently redispatched?
Plants in the TenneT DE zone are frequently ramped up to compensate for curtailed renewables in Northern Germany. This is part of Germany's structural North-South grid bottleneck.