1,970MWh Curtailed
1,398MWh Ramped Up
€0.5MEst. Cost
125 MWPeak Positive
Day-Ahead Spot: -7-150 €/MWh (avg 66)
TSO Breakdown
| TSO | Direction | Measures | Total MWh |
|---|---|---|---|
| TenneT DE | negative | 30 | 46,343 |
| TransnetBW | positive | 23 | 44,350 |
| Amprion | positive | 8 | 13,605 |
| TenneT DE | positive | 6 | 7,587 |
| Amprion | negative | 6 | 2,221 |
| 50Hertz | positive | 3 | 967 |
| TransnetBW | negative | 1 | 171 |
| 50Hertz | negative | 1 | 8 |
Plant-Level Redispatch Measures
| Plant | TSO | Fuel | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|---|
| Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 | TransnetBW | Konventionell | positive | 652 | 15,646 | 22:March-22:March |
| UW Büttel | TenneT DE | negative | 932 | 9,552 | 08:March-22:March | |
| UW Dörpen-West | TenneT DE | negative | 1590 | 9,541 | 22:March-04:March | |
| Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 | TransnetBW | Konventionell | positive | 568 | 6,812 | 10:March-22:March |
| UW Emden-Ost | TenneT DE | negative | 732 | 6,588 | 13:March-22:March | |
| Börse | TenneT DE | Sonstiges | positive | 872 | 6,103 | 08:March-21:March |
| NIEDERAUSSEM_G | Amprion | Konventionell | positive | 280 | 5,040 | 22:March-16:March |
| UW Diele | TenneT DE | negative | 752 | 4,510 | 22:March-04:March | |
| Reservekraftwerk Heilbronn Block 7 | TransnetBW | Konventionell | positive | 239 | 3,699 | 22:March-22:March |
| UW Dörpen-West | TenneT DE | negative | 424 | 3,394 | 09:March-22:March | |
| Reservekraftwerk Heilbronn Block 7 | TransnetBW | Konventionell | positive | 344 | 3,094 | 13:March-22:March |
| Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 | TransnetBW | Konventionell | positive | 194 | 2,423 | 22:March-20:March |
| Heizkraftwerk Altbach/Deizisau Block 2 | TransnetBW | Konventionell | positive | 190 | 2,374 | 09:March-22:March |
| Emsland Block D | Amprion | Konventionell | positive | 444 | 2,220 | 14:March-19:March |
| Heizkraftwerk Altbach/Deizisau Block 2 | TransnetBW | Konventionell | positive | 167 | 2,207 | 22:March-11:March |
| Emsland Block D | Amprion | Konventionell | positive | 662 | 2,151 | 18:March-22:March |
| Börse | TenneT DE | Sonstiges | negative | 595 | 2,084 | 09:March-13:March |
| NIEDERAUSSEM_G | Amprion | Konventionell | positive | 275 | 1,991 | 08:March-16:March |
| NIEDERAUSSEM_G | Amprion | Konventionell | positive | 280 | 1,680 | 16:March-22:March |
| Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 | TransnetBW | Konventionell | positive | 318 | 1,588 | 17:March-22:March |
| AVA Cluster Lehrte | TenneT DE | negative | 186 | 1,300 | 22:March-05:March | |
| Grosskraftwerk Mannheim Block 9 | TransnetBW | Konventionell | positive | 84 | 1,286 | 22:March-16:March |
| UW Emden-Ost | TenneT DE | negative | 407 | 1,220 | 22:March-04:March | |
| Reservekraftwerk Heilbronn Block 7 | TransnetBW | Konventionell | positive | 202 | 1,059 | 16:March-22:March |
| SHN Cluster Klixbüll | TenneT DE | negative | 205 | 1,025 | 17:March-22:March | |
| SHN Cluster Heide West T411 T412 | TenneT DE | negative | 160 | 800 | 17:March-22:March | |
| SHN Cluster Husum Nord | TenneT DE | negative | 160 | 800 | 17:March-22:March | |
| Niederrad 1 | TenneT DE | Konventionell | positive | 33 | 799 | 22:March-22:March |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 191 | 766 | 23:March-10:March |
| Notfall-RD mit AVA | TenneT DE | negative | 71 | 750 | 11:March-22:March | |
| Notfall-RD mit AVA | TenneT DE | negative | 88 | 700 | 22:March-06:March | |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 140 | 664 | 15:March-22:March |
| UW Büttel | TenneT DE | negative | 55 | 656 | 22:March-16:March | |
| AMP_WESTNETZ_NAHE_CR_WIND | Amprion | negative | 245 | 612 | 22:March-00:March | |
| AMP_WESTNETZ_NAHE_CR_WIND | Amprion | negative | 300 | 600 | 20:March-22:March | |
| Kraftwerk Walheim GT D | TransnetBW | Konventionell | positive | 118 | 590 | 22:March-11:March |
| SHN Cluster Süderdonn T411 | TenneT DE | negative | 205 | 562 | 18:March-21:March | |
| SHN Cluster Süderdonn T412 T413 | TenneT DE | negative | 167 | 500 | 19:March-22:March | |
| Pumpspeicherwerk Wehr RZ TNG | TransnetBW | Sonstiges | positive | 245 | 490 | 22:March-00:March |
| Reservekraftwerk Marbach GT 3 | TransnetBW | Konventionell | positive | 77 | 460 | 23:March-11:March |
| SHN Cluster Heide West T411 T412 | TenneT DE | negative | 180 | 450 | 18:March-21:March | |
| Heizkraftwerk_Pforzheim | TransnetBW | Konventionell | positive | 29 | 409 | 22:March-15:March |
| Schwarze Pumpe (Standort) | 50Hertz | Konventionell | positive | 400 | 400 | 15:March-16:March |
| UW Diele | TenneT DE | negative | 126 | 345 | 13:March-15:March | |
| Schkopau | 50Hertz | Konventionell | positive | 109 | 327 | 15:March-19:March |
| AMP_WESTNETZ_TRIER_CR_WIND | Amprion | negative | 156 | 312 | 22:March-00:March | |
| OWP Nordergründe | TenneT DE | negative | 99 | 296 | 19:March-22:March | |
| Linden GKL GT 1 | TenneT DE | Konventionell | positive | 65 | 292 | 15:March-19:March |
| WP Schafflund | TenneT DE | negative | 97 | 290 | 19:March-22:March | |
| Grosskraftwerk Mannheim Block 9 | TransnetBW | Konventionell | positive | 128 | 289 | 19:March-22:March |
How BESS Can Reduce These Costs
Battery Energy Storage Systems at congestion points could have avoided an estimated €0.15M of today's redispatch costs by absorbing excess wind energy locally.
Learn BESS Arbitrage (Free) Stromfee AI PlatformFrequently Asked Questions
How much did redispatch cost on 2026-03-29?
On 2026-03-29, estimated redispatch costs were approximately €0.5 million. This includes €0.2M for renewable curtailment compensation and €0.13M for conventional ramp-up costs.
Which power plants were most affected on 2026-03-29?
The most affected plant was Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 (TransnetBW) with 15,646 MWh of positive redispatch.
What was the electricity spot price on 2026-03-29?
The EPEX Day-Ahead spot price for DE_LU ranged from -7 to 150 €/MWh with an average of 66 €/MWh.