Saturday, August 8, 2026

2026-08-09 →
2,214MWh Curtailed
2,339MWh Ramped Up
€0.7MEst. Cost
188 MWPeak Positive

Day-Ahead Spot: -18-192 €/MWh (avg 98)

TSO Breakdown

TSODirectionMeasuresTotal MWh
TenneT DE negative 3 5,700
Amprion negative 1 114
50Hertz positive 1 8
50Hertz negative 1 6

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
BAG NWAK-Cluster 16 Regensburg-Sittling TenneT DE Erneuerbar negative 250 2,375 07:August-17:August
BAG NWAK-Cluster 17 Altheim TenneT DE Erneuerbar negative 200 1,900 07:August-17:August
BAG NWAK-Cluster 15 Pleinting TenneT DE Erneuerbar negative 150 1,425 07:August-17:August
Datteln_4 Amprion Konventionell negative 114 114 16:August-17:August
Börse 50Hertz Sonstiges positive 34 8 14:August-15:August
Börse 50Hertz Sonstiges negative 23 6 05:August-05:August

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.21M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-08-08?

On 2026-08-08, estimated redispatch costs were approximately €0.7 million. This includes €0.22M for renewable curtailment compensation and €0.3M for conventional ramp-up costs.

Which power plants were most affected on 2026-08-08?

The most affected plant was BAG NWAK-Cluster 16 Regensburg-Sittling (TenneT DE) with 2,375 MWh of negative redispatch.

What was the electricity spot price on 2026-08-08?

The EPEX Day-Ahead spot price for DE_LU ranged from -18 to 192 €/MWh with an average of 98 €/MWh.