SHN Cluster Kummerfeld
16,112Total MWh
38Measures
97 MWAvg Power
38Curtailments
0Ramp-ups
Data: 2024-01-25 to 2026-04-24
Daily Redispatch Volume
| Date | Measures | Total MWh |
|---|---|---|
| 2026-04-24 | 4 | 300 |
| 2026-01-09 | 1 | 196 |
| 2025-12-31 | 1 | 117 |
| 2025-12-27 | 1 | 425 |
| 2025-12-13 | 1 | 125 |
| 2025-11-11 | 1 | 1,140 |
| 2025-11-05 | 1 | 760 |
| 2025-11-03 | 2 | 1,575 |
| 2025-11-02 | 1 | 453 |
| 2025-11-01 | 1 | 349 |
| 2025-10-05 | 1 | 290 |
| 2025-09-26 | 4 | 923 |
| 2025-08-05 | 1 | 894 |
| 2025-08-04 | 2 | 692 |
| 2025-07-05 | 2 | 519 |
| 2025-06-24 | 1 | 275 |
| 2025-06-23 | 1 | 229 |
| 2025-06-12 | 2 | 725 |
| 2025-06-10 | 1 | 365 |
| 2025-05-29 | 1 | 963 |
| 2025-04-13 | 1 | 225 |
| 2025-01-11 | 1 | 925 |
| 2024-11-01 | 2 | 275 |
| 2024-09-05 | 2 | 1,425 |
| 2024-04-09 | 1 | 1,572 |
| 2024-01-25 | 1 | 375 |
Recent Measures
| Date | TSO | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|
| 2026-04-24 | TenneT DE | negative | 100 | 100 | 22:April-23:April |
| 2026-04-24 | TenneT DE | negative | 100 | 100 | 22:April-23:April |
| 2026-04-24 | TenneT DE | negative | 100 | 50 | 21:April-22:April |
| 2026-04-24 | TenneT DE | negative | 100 | 50 | 21:April-22:April |
| 2026-01-09 | TenneT DE | negative | 65 | 196 | 06:January-17:January |
| 2025-12-31 | TenneT DE | negative | 117 | 117 | 05:December-06:December |
| 2025-12-27 | TenneT DE | negative | 100 | 425 | 10:December-15:December |
| 2025-12-13 | TenneT DE | negative | 50 | 125 | 07:December-10:December |
| 2025-11-11 | TenneT DE | negative | 123 | 1,140 | 23:November-09:November |
| 2025-11-05 | TenneT DE | negative | 92 | 760 | 00:November-08:November |
| 2025-11-03 | TenneT DE | negative | 100 | 800 | 23:November-07:November |
| 2025-11-03 | TenneT DE | negative | 100 | 775 | 15:November-23:November |
| 2025-11-02 | TenneT DE | negative | 82 | 453 | 05:November-11:November |
| 2025-11-01 | TenneT DE | negative | 93 | 349 | 05:November-09:November |
| 2025-10-05 | TenneT DE | negative | 145 | 290 | 16:October-18:October |
| 2025-09-26 | TenneT DE | negative | 25 | 25 | 22:September-23:September |
| 2025-09-26 | TenneT DE | negative | 59 | 238 | 18:September-22:September |
| 2025-09-26 | TenneT DE | negative | 81 | 322 | 14:September-18:September |
| 2025-09-26 | TenneT DE | negative | 90 | 338 | 10:September-14:September |
| 2025-08-05 | TenneT DE | negative | 133 | 894 | 08:August-15:August |
| 2025-08-04 | TenneT DE | negative | 141 | 281 | 22:August-00:August |
| 2025-08-04 | TenneT DE | negative | 149 | 411 | 19:August-22:August |
| 2025-07-05 | TenneT DE | negative | 37 | 120 | 17:July-21:July |
| 2025-07-05 | TenneT DE | negative | 94 | 399 | 01:July-06:July |
| 2025-06-24 | TenneT DE | negative | 100 | 275 | 22:June-01:June |
| 2025-06-23 | TenneT DE | negative | 92 | 229 | 04:June-07:June |
| 2025-06-12 | TenneT DE | negative | 93 | 650 | 22:June-05:June |
| 2025-06-12 | TenneT DE | negative | 100 | 75 | 21:June-22:June |
| 2025-06-10 | TenneT DE | negative | 133 | 365 | 19:June-22:June |
| 2025-05-29 | TenneT DE | negative | 133 | 963 | 23:May-06:May |
| 2025-04-13 | TenneT DE | negative | 100 | 225 | 03:April-06:April |
| 2025-01-11 | TenneT DE | negative | 95 | 925 | 11:January-23:January |
| 2024-11-01 | TenneT DE | negative | 77 | 250 | 23:November-02:November |
| 2024-11-01 | TenneT DE | negative | 100 | 25 | 22:November-23:November |
| 2024-09-05 | TenneT DE | negative | 49 | 875 | 22:September-16:September |
| 2024-09-05 | TenneT DE | negative | 100 | 550 | 16:September-22:September |
| 2024-04-09 | TenneT DE | negative | 153 | 1,572 | 23:April-09:April |
| 2024-01-25 | TenneT DE | negative | 88 | 375 | 04:January-09:January |
Frequently Asked Questions
What is the redispatch history of SHN Cluster Kummerfeld?
SHN Cluster Kummerfeld is a Erneuerbar power plant in the TenneT DE grid zone. It has received 38 redispatch instructions totaling 16,112 MWh since 2024-01-25.
Why is SHN Cluster Kummerfeld frequently redispatched?
Plants in the TenneT DE zone are frequently curtailed due to grid congestion from excess renewable generation in Northern Germany. This is part of Germany's structural North-South grid bottleneck.