Würzburg GT 1

KonventionellTenneT DE

1,263Total MWh
16Measures
28 MWAvg Power
4Curtailments
12Ramp-ups

Data: 2024-05-21 to 2026-03-15

Daily Redispatch Volume

DateMeasuresTotal MWh
2026-03-15 1 82
2026-01-30 1 82
2026-01-12 1 210
2025-12-11 1 21
2025-12-02 1 30
2025-11-27 1 12
2025-10-26 1 102
2025-10-25 1 70
2025-10-21 1 102
2025-10-20 3 317
2025-01-05 1 16
2024-12-03 1 23
2024-11-14 1 41
2024-05-21 1 154

Recent Measures

DateTSODirAvg MWMWhTime
2026-03-15 TenneT DE positive 41 82 17:March-19:March
2026-01-30 TenneT DE positive 28 82 23:January-02:January
2026-01-12 TenneT DE positive 30 210 04:January-11:January
2025-12-11 TenneT DE negative 21 21 05:December-06:December
2025-12-02 TenneT DE negative 10 30 07:December-10:December
2025-11-27 TenneT DE positive 25 12 01:November-01:November
2025-10-26 TenneT DE positive 34 102 17:October-20:October
2025-10-25 TenneT DE positive 35 70 17:October-19:October
2025-10-21 TenneT DE positive 51 102 20:October-22:October
2025-10-20 TenneT DE positive 42 116 09:October-12:October
2025-10-20 TenneT DE positive 26 116 07:October-13:October
2025-10-20 TenneT DE positive 24 85 06:October-10:October
2025-01-05 TenneT DE negative 2 16 14:January-22:January
2024-12-03 TenneT DE negative 8 23 05:December-11:December
2024-11-14 TenneT DE positive 24 41 20:November-22:November
2024-05-21 TenneT DE positive 44 154 17:May-20:May

Frequently Asked Questions

What is the redispatch history of Würzburg GT 1?

Würzburg GT 1 is a Konventionell power plant in the TenneT DE grid zone. It has received 16 redispatch instructions totaling 1,263 MWh since 2024-05-21.

Why is Würzburg GT 1 frequently redispatched?

Plants in the TenneT DE zone are frequently ramped up to compensate for curtailed renewables in Northern Germany. This is part of Germany's structural North-South grid bottleneck.