50H_EDIS_CR_SW
• 50Hertz
198Total MWh
1Measures
50 MWAvg Power
1Curtailments
0Ramp-ups
Data: 2026-04-17 to 2026-04-17
Daily Redispatch Volume
| Date | Measures | Total MWh |
|---|---|---|
| 2026-04-17 | 1 | 198 |
Recent Measures
| Date | TSO | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|
| 2026-04-17 | 50Hertz | negative | 50 | 198 | 08:April-12:April |
Frequently Asked Questions
What is the redispatch history of 50H_EDIS_CR_SW?
50H_EDIS_CR_SW is a Erneuerbar power plant in the 50Hertz grid zone. It has received 1 redispatch instructions totaling 198 MWh since 2026-04-17.
Why is 50H_EDIS_CR_SW frequently redispatched?
Plants in the 50Hertz zone are frequently curtailed due to grid congestion from excess renewable generation in Northern Germany. This is part of Germany's structural North-South grid bottleneck.