WP_BEDBURG

ErneuerbarAmprion

634Total MWh
3Measures
18 MWAvg Power
3Curtailments
0Ramp-ups

Data: 2024-04-24 to 2024-04-27

Daily Redispatch Volume

DateMeasuresTotal MWh
2024-04-27 1 2
2024-04-24 2 632

Recent Measures

DateTSODirAvg MWMWhTime
2024-04-27 Amprion negative 3 2 20:April-21:April
2024-04-24 Amprion negative 18 172 22:April-07:April
2024-04-24 Amprion negative 32 460 07:April-22:April

Frequently Asked Questions

What is the redispatch history of WP_BEDBURG?

WP_BEDBURG is a Erneuerbar power plant in the Amprion grid zone. It has received 3 redispatch instructions totaling 634 MWh since 2024-04-24.

Why is WP_BEDBURG frequently redispatched?

Plants in the Amprion zone are frequently curtailed due to grid congestion from excess renewable generation in Northern Germany. This is part of Germany's structural North-South grid bottleneck.