WP Neudersum
16Total MWh
1Measures
16 MWAvg Power
1Curtailments
0Ramp-ups
Data: 2025-09-11 to 2025-09-11
Daily Redispatch Volume
| Date | Measures | Total MWh |
|---|---|---|
| 2025-09-11 | 1 | 16 |
Recent Measures
| Date | TSO | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|
| 2025-09-11 | TenneT DE | negative | 16 | 16 | 09:September-10:September |
Frequently Asked Questions
What is the redispatch history of WP Neudersum?
WP Neudersum is a Erneuerbar power plant in the TenneT DE grid zone. It has received 1 redispatch instructions totaling 16 MWh since 2025-09-11.
Why is WP Neudersum frequently redispatched?
Plants in the TenneT DE zone are frequently curtailed due to grid congestion from excess renewable generation in Northern Germany. This is part of Germany's structural North-South grid bottleneck.