WEISWEILER_F_110

KonventionellAmprion

667Total MWh
5Measures
31 MWAvg Power
0Curtailments
5Ramp-ups

Data: 2024-01-23 to 2024-11-23

Daily Redispatch Volume

DateMeasuresTotal MWh
2024-11-23 1 18
2024-09-23 1 58
2024-04-13 2 120
2024-01-23 1 471

Recent Measures

DateTSODirAvg MWMWhTime
2024-11-23 Amprion positive 23 18 09:November-10:November
2024-09-23 Amprion positive 38 58 09:September-11:September
2024-04-13 Amprion positive 15 8 22:April-22:April
2024-04-13 Amprion positive 25 112 02:April-22:April
2024-01-23 Amprion positive 52 471 05:January-14:January

Frequently Asked Questions

What is the redispatch history of WEISWEILER_F_110?

WEISWEILER_F_110 is a Konventionell power plant in the Amprion grid zone. It has received 5 redispatch instructions totaling 667 MWh since 2024-01-23.

Why is WEISWEILER_F_110 frequently redispatched?

Plants in the Amprion zone are frequently ramped up to compensate for curtailed renewables in Northern Germany. This is part of Germany's structural North-South grid bottleneck.