Silz 2 (TIWAG)
255Total MWh
2Measures
115 MWAvg Power
0Curtailments
2Ramp-ups
Data: 2026-01-22 to 2026-07-27
Daily Redispatch Volume
| Date | Measures | Total MWh |
|---|---|---|
| 2026-07-27 | 1 | 125 |
| 2026-01-22 | 1 | 130 |
Recent Measures
| Date | TSO | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|
| 2026-07-27 | TenneT DE | positive | 100 | 125 | 05:July-07:July |
| 2026-01-22 | TenneT DE | positive | 130 | 130 | 07:January-08:January |
Frequently Asked Questions
What is the redispatch history of Silz 2 (TIWAG)?
Silz 2 (TIWAG) is a Erneuerbar power plant in the TenneT DE grid zone. It has received 2 redispatch instructions totaling 255 MWh since 2026-01-22.
Why is Silz 2 (TIWAG) frequently redispatched?
Plants in the TenneT DE zone are frequently ramped up to compensate for curtailed renewables in Northern Germany. This is part of Germany's structural North-South grid bottleneck.