SWDU_HKW_3B

KonventionellAmprion

482Total MWh
8Measures
36 MWAvg Power
2Curtailments
6Ramp-ups

Data: 2024-02-07 to 2025-02-04

Daily Redispatch Volume

DateMeasuresTotal MWh
2025-02-04 1 22
2024-11-28 1 18
2024-11-27 2 128
2024-11-15 2 276
2024-02-21 1 8
2024-02-07 1 30

Recent Measures

DateTSODirAvg MWMWhTime
2025-02-04 Amprion positive 22 22 10:February-11:February
2024-11-28 Amprion positive 35 18 04:November-05:November
2024-11-27 Amprion positive 31 78 17:November-19:November
2024-11-27 Amprion negative 33 50 07:November-09:November
2024-11-15 Amprion positive 68 85 23:November-00:November
2024-11-15 Amprion positive 64 191 20:November-23:November
2024-02-21 Amprion negative 8 8 15:February-16:February
2024-02-07 Amprion positive 30 30 02:February-03:February

Frequently Asked Questions

What is the redispatch history of SWDU_HKW_3B?

SWDU_HKW_3B is a Konventionell power plant in the Amprion grid zone. It has received 8 redispatch instructions totaling 482 MWh since 2024-02-07.

Why is SWDU_HKW_3B frequently redispatched?

Plants in the Amprion zone are frequently ramped up to compensate for curtailed renewables in Northern Germany. This is part of Germany's structural North-South grid bottleneck.