PSW Rönkhausen

SonstigesAmprion

70Total MWh
1Measures
70 MWAvg Power
0Curtailments
1Ramp-ups

Data: 2026-04-11 to 2026-04-11

Daily Redispatch Volume

DateMeasuresTotal MWh
2026-04-11 1 70

Recent Measures

DateTSODirAvg MWMWhTime
2026-04-11 Amprion positive 70 70 17:April-18:April

Frequently Asked Questions

What is the redispatch history of PSW Rönkhausen?

PSW Rönkhausen is a Sonstiges power plant in the Amprion grid zone. It has received 1 redispatch instructions totaling 70 MWh since 2026-04-11.

Why is PSW Rönkhausen frequently redispatched?

Plants in the Amprion zone are frequently ramped up to compensate for curtailed renewables in Northern Germany. This is part of Germany's structural North-South grid bottleneck.