OWP Albatros AC151 (kurativ)

ErneuerbarTenneT DE

2Total MWh
2Measures
3 MWAvg Power
2Curtailments
0Ramp-ups

Data: 2025-10-01 to 2026-02-04

Daily Redispatch Volume

DateMeasuresTotal MWh
2026-02-04 1 0
2025-10-01 1 2

Recent Measures

DateTSODirAvg MWMWhTime
2026-02-04 TenneT DE negative 1 0 03:February-03:February
2025-10-01 TenneT DE negative 4 2 09:October-09:October

Frequently Asked Questions

What is the redispatch history of OWP Albatros AC151 (kurativ)?

OWP Albatros AC151 (kurativ) is a Erneuerbar power plant in the TenneT DE grid zone. It has received 2 redispatch instructions totaling 2 MWh since 2025-10-01.

Why is OWP Albatros AC151 (kurativ) frequently redispatched?

Plants in the TenneT DE zone are frequently curtailed due to grid congestion from excess renewable generation in Northern Germany. This is part of Germany's structural North-South grid bottleneck.