Netzreservekraftwerk UPM Schongau

KonventionellAmprion

785Total MWh
11Measures
9 MWAvg Power
0Curtailments
11Ramp-ups

Data: 2024-03-29 to 2025-12-11

Daily Redispatch Volume

DateMeasuresTotal MWh
2025-12-11 1 28
2025-12-10 1 12
2025-08-12 2 375
2025-08-11 1 0
2024-09-05 1 22
2024-09-03 1 74
2024-08-23 1 66
2024-05-16 1 56
2024-04-17 1 96
2024-03-29 1 56

Recent Measures

DateTSODirAvg MWMWhTime
2025-12-11 Amprion positive 9 28 08:December-13:December
2025-12-10 Amprion positive 8 12 16:December-17:December
2025-08-12 Amprion positive 19 265 22:August-11:August
2025-08-12 Amprion positive 10 110 10:August-22:August
2025-08-11 Amprion positive 2 0 15:August-15:August
2024-09-05 Amprion positive 7 22 09:September-12:September
2024-09-03 Amprion positive 8 74 07:September-17:September
2024-08-23 Amprion positive 8 66 11:August-20:August
2024-05-16 Amprion positive 8 56 05:May-12:May
2024-04-17 Amprion positive 8 96 22:April-10:April
2024-03-29 Amprion positive 8 56 07:March-14:March

Frequently Asked Questions

What is the redispatch history of Netzreservekraftwerk UPM Schongau?

Netzreservekraftwerk UPM Schongau is a Konventionell power plant in the Amprion grid zone. It has received 11 redispatch instructions totaling 785 MWh since 2024-03-29.

Why is Netzreservekraftwerk UPM Schongau frequently redispatched?

Plants in the Amprion zone are frequently ramped up to compensate for curtailed renewables in Northern Germany. This is part of Germany's structural North-South grid bottleneck.