München Süd GT 61
Konventionell • TenneT DE
278Total MWh
2Measures
52 MWAvg Power
1Curtailments
1Ramp-ups
Data: 2024-02-20 to 2024-08-22
Daily Redispatch Volume
| Date | Measures | Total MWh |
|---|---|---|
| 2024-08-22 | 1 | 190 |
| 2024-02-20 | 1 | 88 |
Recent Measures
| Date | TSO | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|
| 2024-08-22 | TenneT DE | positive | 69 | 190 | 16:August-19:August |
| 2024-02-20 | TenneT DE | negative | 35 | 88 | 11:February-13:February |
Frequently Asked Questions
What is the redispatch history of München Süd GT 61?
München Süd GT 61 is a Konventionell power plant in the TenneT DE grid zone. It has received 2 redispatch instructions totaling 278 MWh since 2024-02-20.
Why is München Süd GT 61 frequently redispatched?
Plants in the TenneT DE zone are frequently ramped up to compensate for curtailed renewables in Northern Germany. This is part of Germany's structural North-South grid bottleneck.