Kirchlengern GT 1
Konventionell • TenneT DE
443Total MWh
3Measures
65 MWAvg Power
0Curtailments
3Ramp-ups
Data: 2025-06-28 to 2025-10-22
Daily Redispatch Volume
| Date | Measures | Total MWh |
|---|---|---|
| 2025-10-22 | 1 | 332 |
| 2025-06-28 | 2 | 111 |
Recent Measures
| Date | TSO | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|
| 2025-10-22 | TenneT DE | positive | 83 | 332 | 05:October-14:October |
| 2025-06-28 | TenneT DE | positive | 65 | 16 | 17:June-17:June |
| 2025-06-28 | TenneT DE | positive | 48 | 95 | 16:June-18:June |
Frequently Asked Questions
What is the redispatch history of Kirchlengern GT 1?
Kirchlengern GT 1 is a Konventionell power plant in the TenneT DE grid zone. It has received 3 redispatch instructions totaling 443 MWh since 2025-06-28.
Why is Kirchlengern GT 1 frequently redispatched?
Plants in the TenneT DE zone are frequently ramped up to compensate for curtailed renewables in Northern Germany. This is part of Germany's structural North-South grid bottleneck.