Heyden
Konventionell • TenneT DE
15,216Total MWh
16Measures
171 MWAvg Power
5Curtailments
11Ramp-ups
Data: 2024-01-04 to 2024-03-20
Daily Redispatch Volume
| Date | Measures | Total MWh |
|---|---|---|
| 2024-03-20 | 2 | 1,898 |
| 2024-03-07 | 1 | 575 |
| 2024-02-27 | 2 | 2,039 |
| 2024-02-20 | 4 | 1,848 |
| 2024-02-19 | 1 | 200 |
| 2024-02-16 | 1 | 1,065 |
| 2024-02-13 | 1 | 925 |
| 2024-01-31 | 1 | 1,255 |
| 2024-01-17 | 1 | 672 |
| 2024-01-04 | 2 | 4,739 |
Recent Measures
| Date | TSO | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|
| 2024-03-20 | TenneT DE | positive | 63 | 95 | 10:March-12:March |
| 2024-03-20 | TenneT DE | positive | 225 | 1,802 | 06:March-14:March |
| 2024-03-07 | TenneT DE | positive | 192 | 575 | 09:March-12:March |
| 2024-02-27 | TenneT DE | positive | 182 | 1,776 | 23:February-08:February |
| 2024-02-27 | TenneT DE | positive | 175 | 262 | 21:February-23:February |
| 2024-02-20 | TenneT DE | positive | 177 | 1,282 | 23:February-06:February |
| 2024-02-20 | TenneT DE | positive | 150 | 112 | 22:February-23:February |
| 2024-02-20 | TenneT DE | negative | 83 | 331 | 17:February-21:February |
| 2024-02-20 | TenneT DE | negative | 35 | 122 | 07:February-11:February |
| 2024-02-19 | TenneT DE | positive | 100 | 200 | 12:February-14:February |
| 2024-02-16 | TenneT DE | negative | 203 | 1,065 | 14:February-20:February |
| 2024-02-13 | TenneT DE | negative | 154 | 925 | 04:February-10:February |
| 2024-01-31 | TenneT DE | positive | 209 | 1,255 | 10:January-16:January |
| 2024-01-17 | TenneT DE | negative | 245 | 672 | 07:January-10:January |
| 2024-01-04 | TenneT DE | positive | 335 | 2,512 | 09:January-17:January |
| 2024-01-04 | TenneT DE | positive | 212 | 2,226 | 07:January-18:January |
Frequently Asked Questions
What is the redispatch history of Heyden?
Heyden is a Konventionell power plant in the TenneT DE grid zone. It has received 16 redispatch instructions totaling 15,216 MWh since 2024-01-04.
Why is Heyden frequently redispatched?
Plants in the TenneT DE zone are frequently ramped up to compensate for curtailed renewables in Northern Germany. This is part of Germany's structural North-South grid bottleneck.