GERSTEINW_K1
Konventionell • Amprion
215Total MWh
1Measures
96 MWAvg Power
0Curtailments
1Ramp-ups
Data: 2024-09-23 to 2024-09-23
Daily Redispatch Volume
| Date | Measures | Total MWh |
|---|---|---|
| 2024-09-23 | 1 | 215 |
Recent Measures
| Date | TSO | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|
| 2024-09-23 | Amprion | positive | 96 | 215 | 04:September-07:September |
Frequently Asked Questions
What is the redispatch history of GERSTEINW_K1?
GERSTEINW_K1 is a Konventionell power plant in the Amprion grid zone. It has received 1 redispatch instructions totaling 215 MWh since 2024-09-23.
Why is GERSTEINW_K1 frequently redispatched?
Plants in the Amprion zone are frequently ramped up to compensate for curtailed renewables in Northern Germany. This is part of Germany's structural North-South grid bottleneck.