Freimann GT12

KonventionellTenneT DE

327Total MWh
3Measures
46 MWAvg Power
1Curtailments
2Ramp-ups

Data: 2024-06-11 to 2024-12-02

Daily Redispatch Volume

DateMeasuresTotal MWh
2024-12-02 1 144
2024-06-17 1 138
2024-06-11 1 45

Recent Measures

DateTSODirAvg MWMWhTime
2024-12-02 TenneT DE negative 48 144 05:December-08:December
2024-06-17 TenneT DE positive 46 138 04:June-07:June
2024-06-11 TenneT DE positive 45 45 17:June-18:June

Frequently Asked Questions

What is the redispatch history of Freimann GT12?

Freimann GT12 is a Konventionell power plant in the TenneT DE grid zone. It has received 3 redispatch instructions totaling 327 MWh since 2024-06-11.

Why is Freimann GT12 frequently redispatched?

Plants in the TenneT DE zone are frequently ramped up to compensate for curtailed renewables in Northern Germany. This is part of Germany's structural North-South grid bottleneck.