Frankfurt West 2

KonventionellTenneT DE

9,894Total MWh
30Measures
23 MWAvg Power
1Curtailments
29Ramp-ups

Data: 2024-04-19 to 2026-04-25

Daily Redispatch Volume

DateMeasuresTotal MWh
2026-04-25 2 18
2025-10-08 1 572
2025-10-07 1 1,056
2025-10-06 1 1,080
2025-10-05 1 1,080
2025-10-04 1 1,200
2025-10-03 1 1,256
2025-10-02 2 1,919
2025-10-01 2 1,095
2025-08-27 1 56
2025-08-25 1 8
2025-03-12 1 22
2025-02-24 1 40
2024-11-04 1 10
2024-08-26 1 66
2024-08-23 1 42
2024-08-21 1 45
2024-08-13 1 115
2024-05-21 2 44
2024-05-15 1 40
2024-05-14 1 15
2024-05-13 1 14
2024-05-07 1 30
2024-05-03 1 45
2024-04-21 1 7
2024-04-19 1 20

Recent Measures

DateTSODirAvg MWMWhTime
2026-04-25 TenneT DE positive 9 9 17:April-18:April
2026-04-25 TenneT DE positive 9 9 17:April-18:April
2025-10-08 TenneT DE positive 44 572 22:October-11:October
2025-10-07 TenneT DE positive 44 1,056 22:October-22:October
2025-10-06 TenneT DE positive 45 1,080 22:October-22:October
2025-10-05 TenneT DE positive 45 1,080 22:October-22:October
2025-10-04 TenneT DE positive 50 1,200 22:October-22:October
2025-10-03 TenneT DE positive 52 1,256 22:October-22:October
2025-10-02 TenneT DE positive 55 1,319 22:October-22:October
2025-10-02 TenneT DE positive 50 600 10:October-22:October
2025-10-01 TenneT DE positive 48 576 22:October-10:October
2025-10-01 TenneT DE positive 40 519 09:October-22:October
2025-08-27 TenneT DE positive 7 56 08:August-16:August
2025-08-25 TenneT DE positive 5 8 14:August-16:August
2025-03-12 TenneT DE positive 11 22 10:March-12:March
2025-02-24 TenneT DE positive 6 40 07:February-19:February
2024-11-04 TenneT DE positive 5 10 11:November-14:November
2024-08-26 TenneT DE positive 16 66 09:August-17:August
2024-08-23 TenneT DE positive 14 42 05:August-18:August
2024-08-21 TenneT DE positive 15 45 07:August-10:August
2024-08-13 TenneT DE positive 23 115 03:August-08:August
2024-05-21 TenneT DE positive 11 33 17:May-20:May
2024-05-21 TenneT DE positive 11 11 16:May-17:May
2024-05-15 TenneT DE positive 7 40 08:May-18:May
2024-05-14 TenneT DE positive 5 15 10:May-13:May
2024-05-13 TenneT DE positive 7 14 05:May-18:May
2024-05-07 TenneT DE positive 10 30 17:May-20:May
2024-05-03 TenneT DE positive 14 45 14:May-18:May
2024-04-21 TenneT DE negative 1 7 07:April-14:April
2024-04-19 TenneT DE positive 20 20 15:April-16:April

Frequently Asked Questions

What is the redispatch history of Frankfurt West 2?

Frankfurt West 2 is a Konventionell power plant in the TenneT DE grid zone. It has received 30 redispatch instructions totaling 9,894 MWh since 2024-04-19.

Why is Frankfurt West 2 frequently redispatched?

Plants in the TenneT DE zone are frequently ramped up to compensate for curtailed renewables in Northern Germany. This is part of Germany's structural North-South grid bottleneck.