BATTERIESPEICHER_NEURATH

SonstigesAmprion

20Total MWh
1Measures
20 MWAvg Power
0Curtailments
1Ramp-ups

Data: 2025-11-13 to 2025-11-13

Daily Redispatch Volume

DateMeasuresTotal MWh
2025-11-13 1 20

Recent Measures

DateTSODirAvg MWMWhTime
2025-11-13 Amprion positive 20 20 14:November-15:November

Frequently Asked Questions

What is the redispatch history of BATTERIESPEICHER_NEURATH?

BATTERIESPEICHER_NEURATH is a Sonstiges power plant in the Amprion grid zone. It has received 1 redispatch instructions totaling 20 MWh since 2025-11-13.

Why is BATTERIESPEICHER_NEURATH frequently redispatched?

Plants in the Amprion zone are frequently ramped up to compensate for curtailed renewables in Northern Germany. This is part of Germany's structural North-South grid bottleneck.