BAG NWAK-Cluster 08 Neufinsing

ErneuerbarTenneT DE

1,300Total MWh
2Measures
150 MWAvg Power
2Curtailments
0Ramp-ups

Data: 2025-07-19 to 2025-08-25

Daily Redispatch Volume

DateMeasuresTotal MWh
2025-08-25 1 800
2025-07-19 1 500

Recent Measures

DateTSODirAvg MWMWhTime
2025-08-25 TenneT DE negative 100 800 07:August-15:August
2025-07-19 TenneT DE negative 200 500 11:July-14:July

Frequently Asked Questions

What is the redispatch history of BAG NWAK-Cluster 08 Neufinsing?

BAG NWAK-Cluster 08 Neufinsing is a Erneuerbar power plant in the TenneT DE grid zone. It has received 2 redispatch instructions totaling 1,300 MWh since 2025-07-19.

Why is BAG NWAK-Cluster 08 Neufinsing frequently redispatched?

Plants in the TenneT DE zone are frequently curtailed due to grid congestion from excess renewable generation in Northern Germany. This is part of Germany's structural North-South grid bottleneck.