AVA Cluster Emden Borssum
8,856Total MWh
10Measures
132 MWAvg Power
10Curtailments
0Ramp-ups
Data: 2025-06-23 to 2025-11-12
Daily Redispatch Volume
| Date | Measures | Total MWh |
|---|---|---|
| 2025-11-12 | 1 | 1,415 |
| 2025-10-28 | 1 | 4,000 |
| 2025-10-27 | 1 | 213 |
| 2025-09-03 | 3 | 790 |
| 2025-08-05 | 1 | 1,062 |
| 2025-07-31 | 1 | 275 |
| 2025-06-23 | 2 | 1,100 |
Recent Measures
| Date | TSO | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|
| 2025-11-12 | TenneT DE | negative | 183 | 1,415 | 15:November-23:November |
| 2025-10-28 | TenneT DE | negative | 291 | 4,000 | 09:October-23:October |
| 2025-10-27 | TenneT DE | negative | 61 | 213 | 23:October-02:October |
| 2025-09-03 | TenneT DE | negative | 127 | 254 | 22:September-00:September |
| 2025-09-03 | TenneT DE | negative | 127 | 286 | 19:September-22:September |
| 2025-09-03 | TenneT DE | negative | 100 | 250 | 15:September-18:September |
| 2025-08-05 | TenneT DE | negative | 177 | 1,062 | 09:August-15:August |
| 2025-07-31 | TenneT DE | negative | 100 | 275 | 11:July-14:July |
| 2025-06-23 | TenneT DE | negative | 50 | 500 | 22:June-08:June |
| 2025-06-23 | TenneT DE | negative | 100 | 600 | 16:June-22:June |
Frequently Asked Questions
What is the redispatch history of AVA Cluster Emden Borssum?
AVA Cluster Emden Borssum is a Erneuerbar power plant in the TenneT DE grid zone. It has received 10 redispatch instructions totaling 8,856 MWh since 2025-06-23.
Why is AVA Cluster Emden Borssum frequently redispatched?
Plants in the TenneT DE zone are frequently curtailed due to grid congestion from excess renewable generation in Northern Germany. This is part of Germany's structural North-South grid bottleneck.