AMP_WESTNETZ_DORTMUND_CR_WIND
• Amprion
3Total MWh
1Measures
1 MWAvg Power
1Curtailments
0Ramp-ups
Data: 2025-07-05 to 2025-07-05
Daily Redispatch Volume
| Date | Measures | Total MWh |
|---|---|---|
| 2025-07-05 | 1 | 3 |
Recent Measures
| Date | TSO | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|
| 2025-07-05 | Amprion | negative | 1 | 3 | 22:July-02:July |
Frequently Asked Questions
What is the redispatch history of AMP_WESTNETZ_DORTMUND_CR_WIND?
AMP_WESTNETZ_DORTMUND_CR_WIND is a Erneuerbar power plant in the Amprion grid zone. It has received 1 redispatch instructions totaling 3 MWh since 2025-07-05.
Why is AMP_WESTNETZ_DORTMUND_CR_WIND frequently redispatched?
Plants in the Amprion zone are frequently curtailed due to grid congestion from excess renewable generation in Northern Germany. This is part of Germany's structural North-South grid bottleneck.