AMP_VSE_CR_SONSTIGE_EE
Sonstiges • Amprion
9Total MWh
3Measures
1 MWAvg Power
3Curtailments
0Ramp-ups
Data: 2025-06-30 to 2025-07-05
Daily Redispatch Volume
| Date | Measures | Total MWh |
|---|---|---|
| 2025-07-05 | 1 | 3 |
| 2025-07-04 | 1 | 3 |
| 2025-06-30 | 1 | 3 |
Recent Measures
| Date | TSO | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|
| 2025-07-05 | Amprion | negative | 1 | 3 | 22:July-02:July |
| 2025-07-04 | Amprion | negative | 1 | 3 | 23:July-02:July |
| 2025-06-30 | Amprion | negative | 1 | 3 | 23:June-02:July |
Frequently Asked Questions
What is the redispatch history of AMP_VSE_CR_SONSTIGE_EE?
AMP_VSE_CR_SONSTIGE_EE is a Sonstiges power plant in the Amprion grid zone. It has received 3 redispatch instructions totaling 9 MWh since 2025-06-30.
Why is AMP_VSE_CR_SONSTIGE_EE frequently redispatched?
Plants in the Amprion zone are frequently curtailed due to grid congestion from excess renewable generation in Northern Germany. This is part of Germany's structural North-South grid bottleneck.