AMP_SYNA_TAUNUS_CR_WIND

ErneuerbarAmprion

11Total MWh
2Measures
8 MWAvg Power
2Curtailments
0Ramp-ups

Data: 2024-02-06 to 2024-11-27

Daily Redispatch Volume

DateMeasuresTotal MWh
2024-11-27 1 3
2024-02-06 1 8

Recent Measures

DateTSODirAvg MWMWhTime
2024-11-27 Amprion negative 6 3 12:November-13:November
2024-02-06 Amprion negative 10 8 10:February-11:February

Frequently Asked Questions

What is the redispatch history of AMP_SYNA_TAUNUS_CR_WIND?

AMP_SYNA_TAUNUS_CR_WIND is a Erneuerbar power plant in the Amprion grid zone. It has received 2 redispatch instructions totaling 11 MWh since 2024-02-06.

Why is AMP_SYNA_TAUNUS_CR_WIND frequently redispatched?

Plants in the Amprion zone are frequently curtailed due to grid congestion from excess renewable generation in Northern Germany. This is part of Germany's structural North-South grid bottleneck.