AMP_LEW_VERTEILNETZ_SUED_CR_PHOTOVOLTAIK
• Amprion
1,041Total MWh
3Measures
107 MWAvg Power
3Curtailments
0Ramp-ups
Data: 2024-09-22 to 2026-04-18
Daily Redispatch Volume
| Date | Measures | Total MWh |
|---|---|---|
| 2026-04-18 | 1 | 64 |
| 2025-07-19 | 1 | 557 |
| 2024-09-22 | 1 | 420 |
Recent Measures
| Date | TSO | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|
| 2026-04-18 | Amprion | negative | 64 | 64 | 13:April-14:April |
| 2025-07-19 | Amprion | negative | 186 | 557 | 10:July-13:July |
| 2024-09-22 | Amprion | negative | 70 | 420 | 08:September-14:September |
Frequently Asked Questions
What is the redispatch history of AMP_LEW_VERTEILNETZ_SUED_CR_PHOTOVOLTAIK?
AMP_LEW_VERTEILNETZ_SUED_CR_PHOTOVOLTAIK is a Erneuerbar power plant in the Amprion grid zone. It has received 3 redispatch instructions totaling 1,041 MWh since 2024-09-22.
Why is AMP_LEW_VERTEILNETZ_SUED_CR_PHOTOVOLTAIK frequently redispatched?
Plants in the Amprion zone are frequently curtailed due to grid congestion from excess renewable generation in Northern Germany. This is part of Germany's structural North-South grid bottleneck.